- Wyoming-based Teton Digital has secured approval to develop a 100MW data center, known as Project Trinity, on a 25-acre site in Dry Fork Township, approximately eight miles south of Tioga, North Dakota. The project will be executed in two phases: the first phase aims to bring 30MW online by Q3/Q4 2025, utilizing existing power from a nearby substation; the second phase involves constructing a new 100MW+ substation in collaboration with local utility MWEC, with the full 100MW facility expected to be operational by the end of 2026. The company is addressing community concerns about potential noise pollution to ensure minimal impact on local residents.