TSMC's $265 Billion Arizona Gigafab: Three Fabs You Can See, Seven on Paper

Fayad Chowdhury

Fayad Chowdhury

Industrial Developments Analyst at aterio.io

Site construction plan from the TSMC Arizona CHIPS Act Draft Environmental Assessment: the 1,129-acre north Phoenix campus outlined in red along Loop 303 and West Carefree Highway, with fab buildings F21P1, F21P2 and F21P3 and support buildings outlined in purple, and a parking area marked for solar panels
  • TSMC's north Phoenix campus has grown from a $12 billion, single-fab announcement in May 2020 to $265 billion and ten planned fabs as of July 16, 2026.
  • Sentinel-2 imagery caught Fab 2 under construction in February 2022, roughly ten months before TSMC announced it in December 2022, and the CHIPS-Act environmental assessment later confirmed the February 2022 construction start.
  • Execution on the first three fabs is real: Fab 1 has been in volume production since late 2024 and is ramping from about 10,000 toward 30,000 wafers per month, Fab 2's building is complete with equipment moving in through September 2026, and Fab 3 is being roofed.
  • Beyond the first three fabs, nothing is going up: Fabs 4 and 6 show early clearing and groundwork but remain pads, Fab 5 shows no activity, and Fabs 7 through 10 were announced on July 16, 2026 with their construction tied to customer demand.
  • TSMC has banked 902 acres south of the original 1,129-acre site for about $197 million, and Chairman C.C. Wei ties the pace of the next fabs to "the market situation and our customers' demand."

Aterio datasets

See the data behind the story

Explore data centers, power, and industrial projects across the US.

In May 2020, TSMC announced its Arizona project as a $12 billion, single-fab plan: 5-nanometer technology, 20,000 wafers per month, over 1,600 direct jobs, construction from 2021 and production in 2024. Six years and four escalations later, the same north Phoenix campus carries a $265 billion announced total and ten planned fabs, a program TSMC has called the largest single foreign direct investment in U.S. history.

Aterio has tracked the campus building by building since ground broke, and Sentinel-2 satellites have recorded it from orbit since January 2021. Both records agree, and they split the announcement cleanly in two: three fabs you can see, one producing, one being tooled, one being roofed, and seven that are dirt or paper. As of mid-July 2026, exactly one of the ten announced fabs is producing chips.

Site construction plan from the TSMC Arizona CHIPS Act Draft Environmental Assessment: the 1,129-acre north Phoenix campus outlined in red along Loop 303 and West Carefree Highway, with fab buildings F21P1, F21P2 and F21P3 and support buildings outlined in purple, and a parking area marked for solar panels

Figure: TSMC Arizona's site construction plan from the CHIPS-Act Draft Environmental Assessment (Figure 2-1): the facility boundary in red, buildings in purple, fabs labeled F21P1 through F21P3, and a parking area slated for solar panels. Source: Draft Environmental Assessment for TSMC AZ, NIST, May 2024, page 24.

Five announcements, one direction

The number has never moved down. On December 6, 2022, TSMC announced a second fab and took the total to roughly $40 billion, with the first fab targeting N4 production in 2024, the second 3nm in 2026, and combined output of more than 600,000 wafers per year. On April 8, 2024, a third fab took it past $65 billion, backed by up to $6.6 billion in direct CHIPS Act funding and up to $5 billion in proposed loans. On March 3, 2025, TSMC and the White House announced an additional $100 billion for three more fabs, advanced packaging and an R&D center, bringing the total to $165 billion. And on July 16, 2026, Chairman C.C. Wei announced another $100 billion at the company's Q2 earnings call: four more fabs, additional advanced packaging, and a target of 2-nanometer and more advanced processes, for a $265 billion program. TSMC also raised its 2026 capital budget to $60-64 billion.

From $12 billion to $265 billion in six years
TSMC's announced Arizona investment at each of its five announcements, in billions of dollars.
From $12 billion to $265 billion in six yearsMay 2020: 12 $B; Dec 2022: plus 28 $B (to 40 $B); Apr 2024: plus 25 $B (to 65 $B); Mar 2025: plus 100 $B (to 165 $B); Jul 2026: plus 100 $B (to 265 $B); Total: 265 $B. Net change: +253 $B.075150225300Value ($B)IncreaseDecrease12May 2020+28Dec 2022+25Apr 2024+100Mar 2025+100Jul 2026265TotalNET +253 $B
TSMC's announced Arizona investment at each of its five announcements, in billions of dollars. focustaiwan.tw

What the ground shows

The campus sits on a 1,129-acre site TSMC purchased on December 9, 2020, undeveloped desert that had been rezoned only weeks earlier. The Sentinel-2 record starts in January 2021 with empty ground and ends in mid-July 2026 with a working semiconductor city.

Animated satellite timelapse of TSMC's north Phoenix gigafab campus from January 2021 to mid-July 2026, showing undeveloped desert transforming into a multi-fab semiconductor campus with completed fab buildings, support facilities and cleared construction pads

Figure: TSMC Arizona campus construction timelapse, January 2021 to mid-July 2026. Captured via Sentinel-2 satellite, sourced through Copernicus; image analysis by Aterio. Source: TSMC, April 2024 expansion announcement.

Four dated satellite frames of TSMC's north Phoenix campus with the six fab footprints (Fab 1 through Fab 6) outlined: May 2021 is bare desert; October 2022 shows Fab 1 nearly complete and Fab 2 under construction; May 2025 shows Fab 1 complete, Fab 2 building and a large solar array; July 2026 shows Fabs 1 and 2 complete, Fab 3 being roofed, Fabs 4 and 6 with early clearing, and Fab 5 still empty

Figure: The same campus at four moments, May 2021 to July 2026, with the six delineated fab footprints outlined. By October 2022 Fab 1 is nearly complete and Fab 2 is under construction, two months before TSMC announced the second fab; by July 2026 Fabs 1 and 2 are complete, Fab 3 is being roofed, Fabs 4 and 6 have begun clearing, and Fab 5 is still bare. Sourced through Planet; image analysis and fab annotations by Aterio. Source: Aterio Industrial Developments dataset.

Fab 1 broke ground in April 2021, and Aterio tracked its building shell as complete by January 2023. TSMC says the fab has been in volume production since late 2024, running 4nm and 5nm FinFET processes at about 10,000 wafers per month and ramping toward 30,000.

Fab 2 is the reason to watch dirt instead of press releases. The CHIPS-Act Draft Environmental Assessment states that "Construction of the Phase 2 building began in February 2022." TSMC announced the fab on December 6, 2022, roughly ten months after the ground started moving. The building is now complete, roofing and cooling equipment were finished by May 2026, and semiconductor manufacturing equipment moves in between July and September 2026. TSMC's stated volume-production date for the 3nm fab is 2028, two years later than the 2026 target it carried when the fab was announced.

Fab 3 began vertical construction in the second half of 2025. By May 2026 the western half of the roof was complete with concrete work continuing on the east, and as of July 14, 2026 roof installation is still progressing. TSMC's public plan has the third fab producing at 2nm or better by the end of the decade, with a timeline the assessment says "may shift subject to demand, market conditions, supply chain availability, and funding."

The other seven fabs

Past Fab 3, the picture thins out. Some early site clearing and groundwork are visible around Fabs 4 and 6, but they still remain pads without foundational concrete or vertical construction. Fab 5, in early planning since at least January 2026, shows no activity yet, and Fabs 7 through 10, announced on July 16, 2026, have no ground broken, their construction tied to customer demand.

Ten fabs announced, one producing
The ten announced Phoenix fabs by what is actually on the ground, mid-July 2026: one producing, two building, two with sitework begun (Fabs 4 and 6), and five not started.
Ten fabs announced, one producingFab 1, producing: 1 fab; Fabs 2-3, building: 2 fabs; Fabs 4 & 6, sitework: 2 fabs; Fabs 5, 7-10, not started: 5 fabs; to Announced: 10 fabsFab 1, producing1 fabFabs 2-3, building2 fabsFabs 4 & 6, sitework2 fabsFabs 5, 7-10, not started5 fabsAnnounced10 fabs
SOURCE: aterio.io
The ten announced Phoenix fabs by what is actually on the ground, mid-July 2026: one producing, two building, two with sitework begun (Fabs 4 and 6), and five not started.

TSMC has the room to build all ten. It bought 902 acres directly south of the existing site for about $197 million at a January 2026 state land auction, and the first three fabs prove the company builds what it announces here. But as Wei put it, "The progress or the schedule, most of the time, depends on the market situation and our customers' demand." The commitment is real; the calendar is not.

The six-year record

Filed milestones in navy; Aterio estimates in amber, dotted with hollow markers.
Project timelineMay 2020: $12B, one fab -> Apr 2021: Fab 1 construction -> Feb 2022: Fab 2 construction -> Dec 2022: Fab 2 announced, $40B -> Apr 2024: Fab 3 announced, $65B -> Late 2024: Fab 1 in production -> Mar 2025: Total to $165B -> H2 2025: Fab 3 construction -> Jul 2026: Fabs 7-10, $265BMay 2020$12B, one fabApr 2021Fab 1 constructionFeb 2022Fab 2 constructionANNOUNCED 10 MONTHS LATERDec 2022Fab 2 announced, $40BApr 2024Fab 3 announced, $65BLate 2024Fab 1 in productionMar 2025Total to $165BH2 2025Fab 3 constructionJul 2026Fabs 7-10, $265B
SOURCE: nist.gov
TSMC Arizona across its five investment announcements: three fabs built or building in six years, with Fab 2 visible under construction ten months before TSMC announced it.

Key project parameters:

  • Operator: TSMC Arizona Corporation, north Phoenix (Maricopa County), along Loop 303 at the campus TSMC brands its Arizona gigafab cluster.
  • Site: 1,129 acres purchased December 9, 2020, plus 902 acres directly south acquired for about $197 million at a January 2026 state land auction for future expansion.
  • Investment: $265 billion announced as of July 16, 2026, up from $12 billion in May 2020.
  • Fabs: 10 announced. Fab 1 producing (4nm/5nm); Fab 2 complete, equipment move-in July-September 2026 (3nm); Fab 3 roofing; Fabs 4 and 6 early clearing/groundwork (still pads); Fab 5 no activity; Fabs 7-10 announced July 2026.
  • Incentives: up to $6.6 billion in direct CHIPS Act funding plus up to $5 billion in proposed loans.

Source: TSMC's May 2020, December 2022, April 2024 and March 2025 announcements; the White House; the Draft Environmental Assessment for TSMC AZ; Focus Taiwan; and the Aterio U.S. Data Center dataset.

Built out, this would be the largest semiconductor manufacturing campus in the United States in Aterio's tracking, roughly 2,000 acres of fabs with a master-planned community, Halo Vista, rising around it.

Bottom line

TSMC's Arizona record cuts both ways, and both edges are sharp. The execution is real: three fabs built or building in five years on ground that was empty desert in January 2021, one of them already shipping advanced-node wafers, another being tooled right now. The gap is real too: seven of the ten announced fabs have no vertical construction yet, and the satellite record does not show nearly as much building as the $265 billion headline implies. The company's own history says the announcements eventually become buildings, but on TSMC's clock, not the press release's: Fab 2 was announced with 2026 production, and its volume date now reads 2028.

What to watch: whether Fabs 4 and 6's pads turn into vertical construction, the first real sign of the next wave; first ground at Fab 5; and permits and dirt for Fabs 7-10. Aterio ran the same satellite-first read on Micron's $100 billion megafab in Clay, New York and on Microsoft's restart of three paused North Carolina campuses: the press release tells you the plan, the dirt tells you the schedule. In Phoenix, the dirt says three fabs, and counting.

Frequently asked questions

How many TSMC fabs are actually built in Arizona?

Of the ten fabs TSMC has announced for its north Phoenix campus, exactly one is producing chips as of mid-July 2026. Fab 1 has been in volume production since late 2024, Fab 2's building is complete with equipment moving in through September 2026, and Fab 3 is being roofed. Fabs 4 and 6 are early-clearing pads with no vertical construction, while Fab 5 and Fabs 7 through 10 show nothing at all.

How much is TSMC investing in Arizona?

TSMC's announced Arizona investment stands at $265 billion as of July 16, 2026, up from a $12 billion, single-fab plan in May 2020. The total climbed through five announcements: roughly $40 billion in December 2022, $65 billion in April 2024, $165 billion in March 2025, and $265 billion in July 2026, supported by up to $6.6 billion in direct CHIPS Act funding.

When will TSMC's Fab 2 in Arizona start production?

TSMC's second Phoenix fab is structurally complete, with semiconductor equipment moving in between July and September 2026. TSMC's stated volume-production date for the 3nm fab is 2028, two years later than the 2026 target attached when the fab was announced in December 2022. Sentinel-2 imagery had caught its construction ten months before that announcement.

Will TSMC build all ten fabs in Arizona?

TSMC's record supports the first three Phoenix fabs, which went from empty desert in January 2021 to one producing, one being tooled, and one being roofed. Beyond them, none show vertical construction yet: Fabs 4 and 6 show early clearing and groundwork but remain pads, Fab 5 shows no activity, and Fabs 7 through 10 were announced in July 2026 with construction tied to customer demand. Chairman C.C. Wei ties the pace to market conditions and customer demand.

Aterio tracks U.S. data center and power projects in real time, from early zoning and permit filings to satellite-confirmed construction. Explore Aterio's latest U.S. Data Center Report for state-by-state insights, provider comparisons, and project pipeline analysis, or schedule a call to see how our data can support your investment analysis.