November 4 Findings: SpaceX-Linked 6 GW Campus in Cochise County, Arizona Targets Initial 1.5 GW by 2027

Aterio Research Team

Research at Aterio

Tombstone Resources concept plan for the AEPCO parcels of Cochise Supercomputer Campus: five 700 MW computing buildings in two groups, with dry coolers, Megapacks and a detention facility

Filings reviewed through November 4, 2026

Aterio datasets

See the data behind the story

The records behind this article live in the US Data Center Database: Locations and Power Demand dataset.

A November 4 statement names SpaceX as the project’s community town-hall host. Phase 1 targets 1.5 GW by H2 2027 with a total investment of $50 billion for this phase alone.

We reviewed the county application and utility letters for Cochise Supercomputer Campus, a proposed nine-building development planned across four phases on approximately 747 acres in Arizona. Tombstone Resources is the applicant. The proposed scale is significant: 1.5 GW of initial electrical demand, rising to 6 GW at full build-out, alongside 24 GWh of battery storage. The application describes grid power as the primary supply, with natural-gas standby generation for critical services. Figures 1 and 2 below show the proposed five-building AEPCO layout and four-building Southline layout, respectively.

Figure 1. AEPCO parcels: conceptual layout for five computing buildings arranged in two groups, with adjacent cooling and battery areas, internal roads and support infrastructure. Source: Tombstone Resources, SU26-22 application, Appendix D, PDF p. 22.

Figure 1. AEPCO parcels: conceptual layout for five computing buildings arranged in two groups, with adjacent cooling and battery areas, internal roads and support infrastructure. Source: Tombstone Resources, SU26-22 application, Appendix D, PDF p. 22.

Figure 2. Southline Transmission parcels: conceptual layout for four computing buildings, with adjacent cooling and battery areas, access roads and support infrastructure. Source: Tombstone Resources, SU26-22 application, Appendix D, PDF p. 23.

Figure 2. Southline Transmission parcels: conceptual layout for four computing buildings, with adjacent cooling and battery areas, access roads and support infrastructure. Source: Tombstone Resources, SU26-22 application, Appendix D, PDF p. 23.

At the concept plans’ 700 MW per building, assumed PUEs of 1.10–1.20 imply approximately 583–636 MW of critical IT capacity per building, with a 609 MW base case.

Illustrative estimates: 700 MW ÷ PUE, assuming the plan label denotes total facility power; not confirmed IT or contracted billable capacity.
ScenarioAssumed PUECritical IT per building
High IT capacity1.10636 MW
Base case1.15609 MW
Low IT capacity1.20583 MW
Illustrative estimates: 700 MW ÷ PUE, assuming the plan label denotes total facility power; not confirmed IT or contracted billable capacity.

During the November 4 CoolFMLive Q&A featuring Cochise County District 3 Supervisor Frank Antenori, a $50 billion investment figure was mentioned in connection with the proposed campus. The phase and spending scope were not specified. Meeting remarks also indicated that the project would pay a higher electricity rate and could support residential bill reductions of up to 20% across SSVEC’s service area. Revenue offsets, including tax revenues, were cited; the mechanism and any customer savings remain to be confirmed.

Power delivery remains conditional. SSVEC and AEPCO’s letters require further studies, infrastructure, executed agreements and approvals. AEPCO describes a future three-party electric service agreement to be submitted to the Arizona Corporation Commission. SSVEC confirms that no agreement has been finalized; docket E-01773A-26-0123 covers the broader cooperative service framework.

SSVEC’s project FAQ reports a preliminary spring 2027 construction start, with the first stage potentially online 3–6 months later and subsequent stages at similar intervals. The schedule remains subject to approvals, load studies and infrastructure completion; it is not a confirmed opening date for the full 1.5 GW first phase.

The next scheduled milestone is the December 9 county planning hearing. If approved and built as proposed, the campus would mark SpaceXAI’s first gigawatt-scale, grid-powered data center campus.

County project documents | SSVEC project FAQ

Keep reading

Optical and thermal aerial views of IREN's Childress campus in Texas, 21 October 2026

Aterio Identifies Potential Horizon 4 Delivery Risk

Our 21 October flyover puts Horizon 4 roughly where Horizon 3 was in late July. Horizons 2 and 3 look on track for Q4 2026; Horizon 4 risks slipping to Q1 2027.

Data Center Research Team

Research at Aterio

Hut 8 River Bend campus in St. Francisville, Louisiana.

Hut 8: River Bend

River Bend is Hut 8’s AI campus in St. Francisville, Louisiana. Phase 1 is a single ~600k sqft building with four data halls and 245 MW of critical IT, backed by 330 MW from Entergy Louisiana. Fluidstack has leased the building for 15 years to run Anthropic workloads, with Google guaranteeing the lease.

Aterio Research Team

Research at Aterio

Project Lighthouse campus in Port Washington, Wisconsin: electrical plan beside satellite imagery from 10 September 2026

Oracle's Project Lighthouse: Power Delays Put 2027 Target at Risk

Project Lighthouse depends on a transmission line Wisconsin regulators have not approved. Our base case: partial power December 2027, full 1.3 GW October 2028.

Aterio Research Team

Research at Aterio