PORTS Technology Campus: Dirt Is Moving

Aterio Research Team

Early site work is underway at PORTS. Planet imagery shows clearing near the first two planned building footprints at SB Energy’s campus in Pike County, Ohio. Ohio EPA lists two active construction-stormwater coverages, issued on 2 and 4 November for 34.4 and 7.59 acres, respectively.1 Our working estimate for the first two PORTS buildings is 450–472 MW of IT capacity each, or roughly 900–944 MW combined. The August grading plan shows 450 MW per building, and SB Energy’s September SEC filing gives about 472 MW per planned building. SB Energy describes Phase 1 as about 800 MW. OpenAI expects that initial capacity to become available in 2028, largely using existing AEP infrastructure. As construction advances, we’ll refine the range using the rated capacity of installed electrical and cooling equipment and confirm operating capacity when commissioning records become available.2
Aterio datasets
See the data behind the story
The records behind this article live in the US Data Center Database: Locations and Power Demand dataset.
SoftBank’s equipment recovery outlook. On 12 November, SoftBank said it expects to recover $5.6 billion of its remaining $6.6 billion in power-equipment advances from the PORTS-Pike generation project, including $3.4 billion in the near term and $2.2 billion by the end of 2027.3 SoftBank separately reported a $3.7 billion procurement loss, including contract changes and settlements, and said the loss was unrelated to PORTS-Pike. Its earnings deck still shows 20-year leases to OpenAI for 8.0 GW of critical IT capacity.4
NVIDIA’s PORTS backstop. In July, The Wall Street Journal reported that NVIDIA was in talks to provide a roughly $250 billion backstop for PORTS.5 The agreements NVIDIA signed on 17 August cap its initial guarantee at $105 billion for about 4.25 GW of IT load. In November, NVIDIA confirmed that the guarantees cover nine buildings and take effect as each is completed and ready for service, with the first guarantee expected to take effect in NVIDIA’s fiscal 2029, which begins in calendar 2028.6
Key permits are still pending. The Army Corps targets 30 November for provisional notification and 29 January 2027 for the final permit decision on the two-building federal review.7 Ohio EPA has closed comments on the main campus water-quality application, and a final decision remains unverified. The separate Artemis power project has a state water-quality hearing on 30 December, with comments open through 7 January 2027.8
What we watch next
If PORTS is on track to bring its first capacity online in 2028, we should see construction on the first two buildings progress from grading to foundation work and structural steel framing in the first half of 2027.9
In Ohio, Senate Finance held its first hearing on 17 November on S.B. 374, which would prohibit new data-center sales-tax exemptions.10 Governor-elect Amy Acton has separately proposed a conditional moratorium.11 If either proposal takes effect, we’ll watch whether it applies to later phases of PORTS. The tax bill could raise costs for phases that would otherwise qualify for exemptions, while a moratorium could push back construction.
Notes
- Ohio Environmental Protection Agency, NPDES Construction Stormwater Register, active records 0GC05095*BG and 0GC05132*AG, accessed November 18, 2026. SB Energy, PORTS-Pike Technology Campus Project Facts.
- Langan and Corgan, Master Grading Plan Exhibit, August 26, 2026, sheet C01-00, Mapping Combined.pdf, p. 37, buildings P1B1 and P1B2, in Ohio EPA water-quality docket 262779A2 (drawing verified from Aterio’s archived copy). SB Energy, Inc., Form S-1/A, September 21, 2026, p. 189 (building-level capacity) and p. 12 (4,248 MW-IT for Buildings 1–9 and 3,776 MW-IT for Buildings 10–17). OpenAI, OpenAI Joins PORTS-Pike Project, August 17, 2026. SB Energy, Project Facts, “Campus Overview” (approximately 800 MW for Phase 1).
- SoftBank Group, Equipment for U.S. AI Data Center (3), revised slide 18, November 12, 2026.
- SoftBank Group, Q2 FY2026 Investor Briefing (Accounting), slide 8, and Q2 FY2026 Earnings Results, slide 45, November 10, 2026.
- Anissa Gardizy, Amrith Ramkumar, and Corrie Driebusch, “Nvidia in Talks With OpenAI to Guarantee $250 Billion Financing for Data Center,” The Wall Street Journal, July 26, 2026.
- NVIDIA, August 17 Form 8-K, Item 1.01, August 17, 2026. NVIDIA, Form 8-K, Exhibit 99.2, CFO Commentary on Third Quarter Fiscal 2027 Results, “Guarantees,” November 17, 2026. NVIDIA, FY2026 Form 10-K, Note 1 (fiscal-year convention).
- Federal Permitting Dashboard, PORTS Technology Campus and U.S. Army Corps of Engineers Section 10/404 Schedule, accessed November 18, 2026.
- Ohio Environmental Protection Agency, PORTS Technology Campus Wetland Permitting and Artemis Power Generation Water-Quality Hearing Notice, accessed November 18, 2026.
- SB Energy, PORTS-Pike Technology Campus Project Facts, “Campus Overview,” accessed November 18, 2026. The 2028 capacity target comes from SB Energy. Foundation work and steel framing in the first half of 2027 are milestones Aterio is watching.
- Ohio Senate, Senate Bill 374, bill summary and committee activity, November 17, 2026.
- Amy Acton for Governor, Call for Conditional Data Center Moratorium Legislation, September 23, 2026. Associated Press, Ohio governor’s race call, November 3, 2026.