Crusoe's Project Jade Data Center Campus Gets Approval in Cheyenne, Wyoming

Daud Shiraz

Data Analyst at aterio.io

Crusoe's Project Jade Data Center Campus Site Plan

Wyoming has greenlit another major data center development. Last week, Laramie County’s Board of Commissioners approved the site plans for Crusoe’s Project Jade data center campus and Tallgrass’ adjacent BFC Power/Cheyenne Power Hub energy generation project. The two projects were reviewed together as a single, co-located development, a 5 building data center campus designed to be supported by a dedicated on-site power plant.

Aterio datasets

See the data behind the story

The records behind this article live in the US Data Center Locations and Power Demand dataset.

Project site of the Crusoe Wyoming Data Center and Tallgrass Power Plant Project

Source: Kimley-Horn. Document retrieved from Laramie County, Wyoming

What Was Approved?

Crusoe: Project Jade (data center campus)

Project Jade is planned as an initial 1.8 GW data center campus near Cheyenne, Wyoming, which can scale up to 10 GW in the future according to a press release by Crusoe.

Key project parameters:

  • Planned capacity: 1.8 GW
  • Planned buildings: 5 (plus supporting infrastructure)
  • Building size: 805,300 sqft each (five buildings total ~4.0M sqft)
  • Data Center campus land area: 600 acres
  • Location: Switchgrass Industrial Park
Site Plan for Crusoe's Project Jade Data Center Campus in Cheyenne, Wyoming

Source: Kimley-Horn. Document retrieved from Laramie County, Wyoming

Tallgrass: BFC Power and Cheyenne Power Hub (power generation)

Tallgrass’ project is a dedicated power plant approved next to the data center development. It is designed to supply large-scale, on-site power for hyperscale loads.

Key project parameters:

  • Planned generation capacity: 2.7 GW
  • Site area: 659 acres
  • Configuration: two natural gas power plants (plus supporting infrastructure)
  • Location: Switchgrass Industrial Park

Source: Kimley-Horn. Document retrieved from Laramie County, Wyoming

Project Timeline

Reported expectations include:

  • Construction to start in Q1 2026
  • First buildings expected to be operational by Q4 2027
Construction Timeline for Crusoe's Data Center Project in Wyoming (Project Jade)

Source: Board of Commissioner meeting Laramie County, Wyoming

Bottom line

Crusoe is already developing two large AI data center campuses in Texas, including Stargate Abilene (with Oracle and OpenAI) and Project Goodnight (end tenant not yet disclosed). Project Jade adds a new, separate campus in Wyoming with 1.8 GW of planned data center capacity, making it one of Crusoe’s largest announced developments to date. There is also a notable design linkage between Crusoe’s Wyoming and Texas work. The Wyoming filings show a 5 building layout of ~805,300 sqft per building, which is quite similar to the newer “rectangular” building footprint Crusoe is using at the Goodnight campus.

Aterio tracks U.S. data center projects in real-time, from early filings and rezoning actions to confirmed construction starts and hyperscale expansions.

Download the latest Data Center Report or schedule a call to explore how emerging campuses like Crusoe's Project Jade fit into the broader AI infrastructure buildout.

Keep reading

Satellite view of the former Portsmouth Gaseous Diffusion Plant in Piketon, Ohio on June 24, 2026: the large white process buildings and paved yards of the existing plant at left, ringed by a perimeter road, with farmland, woodland and open fields covering the surrounding acreage where the PORTS Technology Campus is planned.

SB Energy's 10 GW Ohio Campus Is Raising Capital Faster Than It Is Moving Dirt

SB Energy's 10 GW Piketon campus has a $250B Nvidia backstop in talks and no visible construction since its March groundbreaking.

Juan Felipe Hernandez

Juan Felipe Hernandez

Data Center Analyst at aterio.io

Site construction plan from the TSMC Arizona CHIPS Act Draft Environmental Assessment: the 1,129-acre north Phoenix campus outlined in red along Loop 303 and West Carefree Highway, with fab buildings F21P1, F21P2 and F21P3 and support buildings outlined in purple, and a parking area marked for solar panels

TSMC's $265 Billion Arizona Gigafab: Three Fabs You Can See, Seven on Paper

TSMC's Arizona gigafab is now a $265 billion commitment, but just three of the ten announced fabs show construction on the ground.

Fayad Chowdhury

Fayad Chowdhury

Industrial Developments Analyst at aterio.io

Aerial view of a Microsoft data center campus surrounded by farmland, with rows of low white server buildings, backup generator yards and electrical substations under a cloudy sky.

Microsoft Restarts the Three Ohio Campuses It Cancelled in 2025, Roughly 869 MW

Microsoft cancelled roughly 869 MW of Ohio data center capacity in April 2025, and all three Licking County campuses are now grading toward a 2029 target.

Javier Reyes

Javier Reyes

Data Analyst at aterio.io