Market brief, Wyoming
Data Centers in Wyoming
Wyoming ranks 19th nationally for data center pipeline capacity, with 7,094 MW across 58 projects, 1% of the national total.
By the Aterio data team. Data as of .
Scale
- Data centers tracked
- 59
- Data center capacity*
- 7,094MW
- Data center space*
- 9.7M sq ft
- Average operational size
- 166,088sq ft
Pipeline by stage
- In the pipeline
- 58
- Operational
- 14
- Under construction
- 11
- Announced
- 33
* Pipeline only: operational, under construction and announced projects. One other tracked project is land bank, delayed, withdrawn or cancelled.
How Wyoming compares
The Wyoming mix tracks the national pipeline: 57% of its projects are announced, against 60% across the US.
| Top states by estimated MW | Est. MW | Facilities |
|---|---|---|
| 1.Texas | 151,955 MW | 1,431 |
| 2.Virginia | 65,512 MW | 1,074 |
| 3.Utah | 46,575 MW | 236 |
| 4.Pennsylvania | 35,641 MW | 426 |
| 5.Georgia | 32,793 MW | 464 |
| 19.Wyoming | 7,094 MW | 58 |
Top five states by pipeline capacity, and Wyoming, estimated MW.
Where it is being built
Two counties carry Wyoming: Natrona County (3,100 MW) and Laramie County (2,434 MW), 78% of the pipeline.
| Top counties by estimated MW | Est. MW | Facilities |
|---|---|---|
| 1.Natrona County | 3,100 MW | 15 |
| 2.Laramie County | 2,434 MW | 33 |
| 3.Uinta County | 1,200 MW | 6 |
Top three counties by estimated MW, among those with three or more projects. Projects with no county are left out.
Who is building
Google leads with 1,600 MW, ahead of Prometheus Hyperscale with 1,200 MW. The five largest named providers hold 75% of the Wyoming pipeline.
| Top providers by estimated MW | Est. MW | Facilities |
|---|---|---|
| 1.Google | 1,600 MW | 4 |
| 2.Prometheus Hyperscale | 1,200 MW | 6 |
| 3.Microsoft | 1,140 MW | 19 |
| 4.Vantage Data Centers | 960 MW | 4 |
| 5.Related Digital | 420 MW | 4 |
Top five providers by estimated MW, among those with three or more projects. Undisclosed providers are left out.
From the dataset
Largest data centers in Wyoming
Ranked by estimated capacity. Each facility's power and size are available in the full dataset.
- 1.Wyoming Crusoe DC-4Google · Casper, Natrona CountyAnnounced
- 2.Wyoming Crusoe DC-1Google · Casper, Natrona CountyUnder construction
- 3.Wyoming Crusoe DC-3Google · Casper, Natrona CountyAnnounced
- 4.Wyoming Crusoe DC-2Google · Casper, Natrona CountyAnnounced
- 5.Project Latigo Data Center 1Vantage Data Centers · Cheyenne, Laramie CountyAnnounced
Free sample
- AI Data Center (Cheyenne) - Building 1Facebook · Cheyenne, Laramie CountyPower 90 MWSize 357,500 sq ftUnder construction
- Utility
- Cheyenne Light Fuel & Power
- Announced
- Jul 2, 2024
- Expected online
- Dec 30, 2026