Market brief, Oregon

Data Centers in Oregon

Oregon ranks 20th nationally for data center pipeline capacity, with 7,054 MW across 158 projects, 1% of the national total.

By the Aterio data team. Data as of .

Scale

Data centers tracked
160
Data center capacity*
7,054MW
Data center space*
32.0M sq ft
Average operational size
211,588sq ft

Pipeline by stage

In the pipeline
158
Operational
109
Under construction
12
Announced
37

* Pipeline only: operational, under construction and announced projects. The other 2 tracked projects are land bank, delayed, withdrawn or cancelled.

How Oregon compares

In Oregon, 69% of projects are already operational, against 29% nationally. Announced projects make up 23% of the total, below the national 59%.

Top states by estimated MWEst. MWFacilities
1.Texas152,429 MW1,431
2.Virginia64,312 MW1,071
3.Utah46,575 MW236
4.Pennsylvania33,466 MW430
5.Georgia32,790 MW481
20.Oregon7,054 MW158

Top five states by pipeline capacity, and Oregon, estimated MW.

Where it is being built

Morrow County alone holds 52% of the Oregon pipeline, 3,675 MW across 61 projects.

Top counties by estimated MWEst. MWFacilities
1.Morrow County3,675 MW61
2.Umatilla County1,743 MW29
3.Washington County748 MW34
4.Crook County491 MW15
5.Wasco County354 MW6

Top five counties by estimated MW, among those with three or more projects.

Who is building

Amazon AWS alone holds 70% of the Oregon pipeline, 4,964 MW across 83 projects.

Top providers by estimated MWEst. MWFacilities
1.Amazon AWS4,964 MW83
2.Facebook403 MW10
3.Google354 MW6
4.Rowan Digital Infrastructure300 MW4
5.STACK Infrastructure237 MW8

Top five providers by estimated MW, among those with three or more projects. Undisclosed providers are left out.

From the dataset

Largest data centers in Oregon

Ranked by estimated capacity. Each facility's power and size are available in the full dataset.

  1. 1.The Dalles Data Center Building 5Google · The Dalles, Wasco CountyOperational
  2. 2.The Dalles Data Center Building 6Google · The Dalles, Wasco CountyOperational
  3. 3.Amazon AWS PDX - 73577 Lewis 1Amazon AWS · Boardman, Morrow CountyOperational
  4. 4.The Dalles Data Center Building 4Google · The Dalles, Wasco CountyOperational
  5. 5.Boardman Airport South Data Center 4Amazon AWS · Boardman, Morrow CountyAnnounced

Free sample

  • SDC Umatilla Building 2Sabey Data Centers · Umatilla, Umatilla CountyPower 75 MWSize 357,270 sq ftAnnounced
    Utility
    Not assigned
    Expected online
    Jun 1, 2030
  • The Dalles Data Center Building 3Google · The Dalles, Wasco CountyPower 28 MWSize 104,255 sq ftOperational
    Utility
    Northern Wasco County PUD
    Online
    Oct 30, 2006

Frequently asked questions

Data centers in other states

US Data Centers: Market Analysis & Growth Forecast