It costs $1 Billion to Transmit 1,000 MW

Aterio Research Team

Aterio Research Team

Research at Aterio

It costs  $1 Billion to Transmit 1,000 MW

Dominion estimates that regional transmission upgrades alone will require nearly $10 billion in investments for 10,000 megawatts (MW)

Breaking Down the Numbers

To put this in perspective:

  • Incremental demand: 10,000 MW.
  • Estimated cost: $10 billion.
  • Cost per 1,000 MW: $1 billion.

Aterio datasets

See the data behind the story

The records behind this article live in the US Data Center Locations and Power Demand dataset.

This metric of $1 billion per 1,000 MW serves as a useful benchmark for understanding the financial implications of scaling transmission infrastructure. While Dominion's operations represent a specific geography and regulatory environment, the costs provide valuable insight for other utilities facing similar challenges.

Comparable Costs in Other Regions

In Ohio, for example, AEP Ohio has already connected 5,000 MW of incremental load. Experts anticipate that adding the next 5,000–6,000 MW of capacity will mirror Dominion's cost estimates, with investments likely approaching $10 billion for a similar load increase. This reinforces the broader trend: as demand for electricity grows, utilities must allocate substantial resources to ensure grid reliability and capacity.


$45 Billion

Aterio estimates that 45,000 MW of new data centers have been announced but are not yet under construction. Applying the $1 billion per 1,000 MW benchmark, the transmission infrastructure needed to support these data centers could require an astounding $45 billion in investment. This highlights the immense financial scale of supporting the ongoing growth of digital infrastructure and the need for careful planning in the energy sector.

Keep reading

Satellite view of the former Portsmouth Gaseous Diffusion Plant in Piketon, Ohio on June 24, 2026: the large white process buildings and paved yards of the existing plant at left, ringed by a perimeter road, with farmland, woodland and open fields covering the surrounding acreage where the PORTS Technology Campus is planned.

SB Energy's 10 GW Ohio Campus Is Raising Capital Faster Than It Is Moving Dirt

SB Energy's 10 GW Piketon campus has a $250B Nvidia backstop in talks and no visible construction since its March groundbreaking.

Juan Felipe Hernandez

Juan Felipe Hernandez

Data Center Analyst at aterio.io

Site construction plan from the TSMC Arizona CHIPS Act Draft Environmental Assessment: the 1,129-acre north Phoenix campus outlined in red along Loop 303 and West Carefree Highway, with fab buildings F21P1, F21P2 and F21P3 and support buildings outlined in purple, and a parking area marked for solar panels

TSMC's $265 Billion Arizona Gigafab: Three Fabs You Can See, Seven on Paper

TSMC's Arizona gigafab is now a $265 billion commitment, but just three of the ten announced fabs show construction on the ground.

Fayad Chowdhury

Fayad Chowdhury

Industrial Developments Analyst at aterio.io

Aerial view of a Microsoft data center campus surrounded by farmland, with rows of low white server buildings, backup generator yards and electrical substations under a cloudy sky.

Microsoft Restarts the Three Ohio Campuses It Cancelled in 2025, Roughly 869 MW

Microsoft cancelled roughly 869 MW of Ohio data center capacity in April 2025, and all three Licking County campuses are now grading toward a 2029 target.

Javier Reyes

Javier Reyes

Data Analyst at aterio.io