Valara Holdings High Performance Compute Center (BTM)
Project information
NorthMark Strategies
Spartanburg, South Carolina
Quick Facts
Energy Source
Natural Gas
Contracted Power
Agreement Type
N/A
Total Cost
Project Footprint
N/A
Site Boundary
N/A
Plants (2)
Valara Holdings High Performance Compute Center (BTM) - Turbines
Spartanburg, South Carolina · 4000 S Pine St, Spartanburg, SC 29302, USA
Phases (1)
Nameplate Power (MW)
Nameplate Power MW (Summer)
Nameplate Power MW (Winter)
Construction %
Activation
~Sun Dec 31 2028
Announced Date
Wed May 06 2026
Construction Start
~Wed Apr 15 2026
Latest Satellite Picture
Mon Oct 19 2026
Valara Holdings High Performance Compute Center (BTM) - Engines
Spartanburg, South Carolina · 4000 S Pine St, Spartanburg, SC 29302, USA
Phases (1)
Nameplate Power (MW)
Nameplate Power MW (Summer)
Nameplate Power MW (Winter)
Construction %
Activation
N/A
Announced Date
Wed May 06 2026
Construction Start
~Thu Oct 23 2025
Latest Satellite Picture
Mon Oct 19 2026
Companies Involved
- Developer Companies
- NorthMark Strategies
- Customer Companies
- NorthMark Strategies
- Construction Equipment Provider
- Jacobs, Baker Hughes, GE Vernova, Cummins Inc.
- Project Financing Companies
- N/A
Agreement And Sources
- Agreement Type
- N/A
- Agreement URL
- N/A
- Project Source URL
- N/A
Explore Similar Assets
Compare nearby and same-company power generation projects
Other projects from NorthMark Strategies
US Power Generation: Market Analysis & Growth Forecast
Get exclusive insights on the expanding US power generation market, with detailed analysis of solar, wind, storage, and natural gas projects, power capacity, and construction status across all states.