Market brief, Ohio
Data Centers in Ohio
Ohio ranks sixth nationally for data center pipeline capacity, with 31,096 MW across 374 projects, 5% of the national total.
By the Aterio data team. Data as of .
Scale
- Data centers tracked
- 395
- Data center capacity*
- 31,096MW
- Data center space*
- 70.2M sq ft
- Average operational size
- 171,889sq ft
Pipeline by stage
- In the pipeline
- 374
- Operational
- 116
- Under construction
- 71
- Announced
- 187
* Pipeline only: operational, under construction and announced projects. The other 21 tracked projects are land bank, delayed, withdrawn or cancelled.
How Ohio compares
Ohio is further along than the US as a whole: only 50% of its projects are still announced, against 59% nationally.
| Top states by estimated MW | Est. MW | Facilities |
|---|---|---|
| 1.Texas | 152,429 MW | 1,431 |
| 2.Virginia | 64,312 MW | 1,068 |
| 3.Utah | 46,575 MW | 236 |
| 4.Pennsylvania | 33,239 MW | 427 |
| 5.Georgia | 32,790 MW | 481 |
| 6.Ohio | 31,096 MW | 374 |
Top five states by pipeline capacity, and Ohio, estimated MW.
Where it is being built
Two counties carry Ohio: Pike County (8,024 MW) and Licking County (7,534 MW), 50% of the pipeline.
| Top counties by estimated MW | Est. MW | Facilities |
|---|---|---|
| 1.Pike County | 8,024 MW | 17 |
| 2.Licking County | 7,534 MW | 116 |
| 3.Butler County | 1,862 MW | 25 |
| 4.Fayette County | 1,645 MW | 23 |
| 5.Franklin County | 1,582 MW | 41 |
Top five counties by estimated MW, among those with three or more projects. Projects with no county are left out.
Who is building
Amazon AWS leads with 8,363 MW, ahead of SB Energy with 8,024 MW. The five largest named providers hold 75% of the Ohio pipeline.
| Top providers by estimated MW | Est. MW | Facilities |
|---|---|---|
| 1.Amazon AWS | 8,363 MW | 135 |
| 2.SB Energy | 8,024 MW | 17 |
| 3.Facebook | 3,422 MW | 40 |
| 4.Google | 1,831 MW | 21 |
| 5.EdgeConnex | 1,577 MW | 8 |
Top five providers by estimated MW, among those with three or more projects. Undisclosed providers are left out.
From the dataset
Largest data centers in Ohio
Ranked by estimated capacity. Each facility's power and size are available in the full dataset.
- 1.Ports Technology Campus DC 11SB Energy · Piketon, Pike CountyAnnounced
- 2.Ports Technology Campus DC 14SB Energy · Piketon, Pike CountyAnnounced
- 3.Ports Technology Campus DC 7SB Energy · Piketon, Pike CountyAnnounced
- 4.Ports Technology Campus DC 16SB Energy · Piketon, Pike CountyAnnounced
- 5.Ports Technology Campus DC 15SB Energy · Piketon, Pike CountyAnnounced
Free sample
- NEO-01 Perkins Township Data CenterAligned Data Centers · Sandusky, Erie CountyPower 108 MWSize 214,000 sq ftUnder construction
- Utility
- Ohio Edison Co
- Expected online
- Dec 31, 2026
- CMH01 Columbus OH Data Center Phase 15C Data Centers · Springfield, Clark CountyPower 100 MWSize 320,000 sq ftUnder construction
- Utility
- Not assigned
- Announced
- Jun 19, 2024
- Expected online
- Nov 15, 2026
- Amazon AWS - Beech Building 3Amazon AWS · Johnstown, Licking CountyPower 60 MWSize 215,500 sq ftOperational
- Utility
- Ohio Power Co
- Online
- Nov 15, 2024
Frequently asked questions
Data centers in other states
US Data Centers: Market Analysis & Growth Forecast
Get exclusive insights on the rapidly expanding US data center market, with detailed analysis of facilities, power capacity and strategic expansions across Ohio and the rest of the US.