St. Joseph, AWS Campus
Amazon AWS • IN
AWS has confirmed that 7 of 18 buildings from Phase 1 of its Project Rainer–St. Joseph campus are now active, with Phase 2 construction underway. The full development spans 30 buildings totaling 2.2 GW, and Aterio estimates the site will reach 1 GW of active capacity by the end of 2025.
10/31/2025
Future Capacity
Amazon AWS • TX
Amazon’s AWS added 3.8 GW of new capacity over the past year and plans to double its data center footprint within two years, supported by a $125B capex budget for 2025 with additional increases planned for 2026. On the latest earnings call, AWS projected over 1 GW of new capacity activations in Q4 2025, compared to Aterio’s estimate of roughly 1.3 GW.
10/31/2025
OpenAI Stargate - Michigan Campus
Oracle • MI
Following several rezoning rejections, OpenAI, Oracle, and Related Digital have confirmed plans for the Stargate Campus in Benton, Michigan, a 1.5 million sq ft, 1 GW+ AI-focused data center development. The project is slated for activation by Q4 2027, and follows OpenAI’s recent wave of five new campus announcements across the U.S.
10/31/2025
DeForest Campus
QTS Data Centers • WI
QTS Data Centers has initiated discussions with the Village of DeForest about annexing land for a proposed multibillion dollar data center campus; the company plans to submit a zoning application in November.
10/31/2025
Grayslake, T5 Campus
T5 Data Centers • IL
T5 Data Centers has begun construction on its 1.2 GW Chicago IV campus, located in Northlake, Illinois. Satellite imagery from Oct 26, 2025 confirms land grading activity across multiple parcels, with at least three building pads visible. The first facility is scheduled to become operational by 2027
10/31/2025
Wisconsin 1, Microsoft Campus
Microsoft • WI
Microsoft plans to double its data center footprint within two years and expand AI capacity by over 80% in fiscal 2026, responding to surging demand for AI services. The company spent a record $34.9B in Q1 FY2026 capex, including $11.1B in data center leases, announced its 2 GW Fairwater facility in Wisconsin, and deployed its first large-scale NVIDIA GB300 cluster, as Azure grew 40% year-over-year despite ongoing capacity constraints.
10/31/2025
ACG Conyers Manufacturing Facility
ACG • GA
ACG is investing $200 million to establish its first U.S. capsule manufacturing facility in Conyers, Georgia. The state-of-the-art plant will create over 200 jobs and is slated to begin operations by early 2027.
10/30/2025
Good Samaritan Hospital San Jose
HCA Healthcare • CA
HCA Healthcare’s (HCA) Good Samaritan Hospital in San Jose, CA, has broken ground on a $1.3 billion campus expansion. The redevelopment will add a new 715,000 sq. ft. medical center with 234 private patient rooms, upgrading facilities to modern standards.
10/30/2025
Loxley Logistics Center
Crown West Realty • AL
Crown West Realty broke ground on the first building at Loxley Logistics Center, a new 200-acre industrial park in Baldwin County, Alabama. The initial 162,000 sq. ft. cross-dock warehouse will be delivered by late 2026, positioning Loxley as a rising logistics hub on the Gulf Coast
10/30/2025
Hermitage Logistics Hub
Lovett Industrial • TN
Lovett Industrial broke ground on the Hermitage Logistics Hub near Nashville, TN, a 213,840 sq ft Class A warehouse on a 52-acre site. The rear-load facility is scheduled for completion by Q4 2026 to serve rising logistics demand in the growing Nashville market
10/30/2025
Electrolux Kinston Expansion
Electrolux Consumer Products • NC
Electrolux is expanding its Kinston, NC manufacturing plant with a $23.7 million investment. The project will add 30,000 sq. ft. of manufacturing space and create 74 new jobs as the facility ramps up production of stainless steel tub dishwashers
10/30/2025
Georgia 2, Microsoft Campus
Microsoft • GA
New developments spotted at Microsoft’s Georgia 2 Campus in Palmetto, three additional data center buildings have been identified through recent satellite imagery and confirmed by the traffic study for the Microsoft CCO06 Data Center.
10/24/2025
Talkington Campus
CyrusOne • IL
CyrusOne plans a $500 million, 280-acre data center campus in Sangamon County, Illinois, featuring six 250,000 sqft buildings and 600 MW power demand, with construction expected to start in 2026 and completion in 2027.
10/22/2025
Merck Virginia Manufacturing Facility
Merck & Co., Inc. • VA
Merck has broken ground on a $3B, 400,000-sq-ft pharmaceutical manufacturing facility in Elkton, VA, expected to create 8,000 construction jobs and 500 permanent roles upon completion.
10/22/2025
Carolina Renewable Orangeburg Facility
Carolina Renewable Products • SC
Carolina Renewable Products is developing a $280 million renewable diesel and biochar plant in Orangeburg County, South Carolina, creating 155 jobs. The facility will convert sustainable wood biomass into renewable diesel, biochar, and wood vinegar, serving as the company’s headquarters and training hub. Operations are expected to begin in late 2026.
10/22/2025
Morgan County Campus
Google • IN
The 390-acre, four-building data center campus in Morgan County, Indiana has now been confirmed to be developed by Google. Aterio captured the project in February, when early rezoning filings were in process, and Google’s involvement was identified well before the county’s official confirmation this week.
10/22/2025
Project Horizon
CoreWeave • TX
Poolside and CoreWeave are jointly developing Project Horizon, a 2-gigawatt AI campus in Pecos County, Texas, designed for frontier-scale model training. The site will be powered by on-site natural-gas turbines with grid-redundant backup and battery storage, developed in eight 250-megawatt phases, with the first phase scheduled to go live in 2027.
10/22/2025
Project Skyway
Ryan Companies • MN
Ryan Companies has proposed Project Skyway, a 482-acre data center campus in Pine Island, Minnesota, totaling about 3 million sqft across up to three stories. Development applications are expected by late 2025, with power supplied by Xcel Energy.
10/22/2025
Ahold Delhaize Burlington Distribution Center
Ahold Delhaize USA • NC
Ahold Delhaize USA plans a $860M, 1M sq ft automated distribution center in Burlington, NC, supporting Food Lion and other grocery brands, with construction starting 2026 and operations in 2029.
10/22/2025
Atlas Argo Campus
Atlas Agro • WA
Atlas Agro has proposed a five-building data center campus in Richland, Washington, each 500,000 sq ft. Construction is expected to begin in 2027 near the company’s planned green fertilizer plant.
10/22/2025
Amazon Naugatuck Fulfillment Center
Amazon • CT
Amazon has broken ground on a 3.2M sqft robotics fulfillment center on the Waterbury-Naugatuck line, slated to open in 2027 and create 1,000 full-time jobs.
10/22/2025
Averitt Express Mississippi Expansion
Averitt Express • MS
Rankin County is set for growth as Averitt Express expands with a 150,000 sqft logistics hub, promising fresh jobs and a boost to Mississippi’s supply chain sector with a $9.6 million investment.
10/20/2025
Lupin Coral Springs Manufacturing Facility
Lupin Limited • FL
Lupin is establishing a $250M, 70,000-SF pharma facility in Coral Springs, Florida, to manufacture respiratory drugs for U.S. patients. The project will create 200 jobs by 2030 and bolster domestic pharmaceutical production.
10/17/2025
Aligned Frederick Campus
Aligned Data Centers • MD
Aligned Data Centers has begun construction on three additional buildings totaling 1,149,000 sq ft at its Frederick, Maryland campus. These new facilities, approved in May 2025, expand the site to a total of four buildings with a combined planned capacity of 264 MW.
10/16/2025
El Paso, Meta Campus
Facebook • TX
Meta has broken ground on its third Texas data campus in El Paso, investing $1.5 billion for a new AI-driven development. The campus spans 1,000 acres and is scalable to 1 gigawatt, highlighting Meta’s commitment to expanding tech infrastructure across West Texas.
10/16/2025
Energy Way Industrial Park Campus
Amazon AWS • NC
Amazon is launching a $10 billion AI/cloud campus in Richmond County, NC, located next to Duke Energy’s Sherwood H. Smith Jr. energy complex, a gas-fired plant with capacity exceeding 1,200 MW . The development, planned on roughly 800 acres in Energy Way Industrial Park, will feature 20 data center buildings, each about 200,000 to 250,000 sq ft . Satellite imagery from Oct 14, 2025 confirms large-scale site clearing began Oct 1, marking the commencement of groundwork for one of North Carolina’s most ambitious tech infrastructure projects.
10/15/2025
AWS Mattameade Campus
Amazon AWS • VA
Satellite imagery from October 9, 2025 confirms construction has begun on a new 770 MW data center campus, with site clearing underway for Buildings 1 and 2 and advanced concrete work visible at the planned substation. The full project is slated to deliver 770 MW of capacity by 2027.
10/15/2025
Kimberly-Clark Warren Distribution Center
Kimberly-Clark Corporation • OH
Kimberly-Clark (KMB) plans a $160 million, 500,000-SF distribution center beside its upcoming $800 million Warren manufacturing plant, set to break ground in early 2026 and create 65 new jobs.
10/15/2025
Stafford Technology Campus
STACK Infrastructure • VA
STACK Infrastructure has begun construction on its 1 GW+ Stafford Technology Campus at 196–344 Eskimo Hill Rd, Stafford, VA, planned to include 19 buildings totaling 5.8 M sq ft. Satellite imagery from Oct 9, 2025 confirms site grading completed with a defined building pad and perimeter access roads for the first building, while site clearing is underway for the second. The campus will draw committed power from six 300 MW substations supplied by Dominion Energy, positioning it among the largest planned data center developments in Virginia.
10/14/2025
HyperGrid Data Center Campus
FERMI America • TX
Satellite imagery from October 11, 2025 confirms site clearing activity underway at Power Blocks A and B of Project Matador, which began during the fourth week of September. These two blocks will host six (6) 6-on-1 combined-cycle generator configurations using Siemens Energy SGT-800 turbines, representing the first phase of the development. At full operation, this phase is expected to provide approximately 2.25 - 2.5 GW of nameplate capacity, almost a quarter of the project’s planned 11,000 MW total.
10/14/2025
Central Pike Logistics Center
Stream Realty Partners • TN
Stream Realty Partners has begun construction on the 1.1 million square-foot Central Pike Logistics Center in Lebanon, Tennessee, marking its first industrial project in the Nashville market. The two-building speculative development spans 89 acres, with Cushman & Wakefield overseeing leasing and Mycon Construction as the general contractor.
10/14/2025
Canton, AWS Campus
Amazon AWS • MS
Satellite imagery from October 4, 2025 confirms large-scale land grading on five additional data centers at AWS's Canton campus. The site currently hosts one active facility, with four in advanced construction expected to come online by Q4 2025. The full master plan includes up to 16 buildings spread across 927 acres. For this campus AWS operates under long-term Power Purchase Agreements (PPAs) with Entergy, securing renewable energy, primarily sola, to supply the site through dedicated grid infrastructure.
10/10/2025
Charleston Aerospace Facility
Eaton • SC
Eaton (ETN) is investing $46 million to build a new aerospace manufacturing facility next to its North Charleston site, creating over 50 jobs. The plant will handle machining, additive manufacturing, and hydraulic system testing, with operations expected to begin in 2028.
10/10/2025
Rumble Technology Campus
Google • GA
Google has purchased 950 acres in Monroe County, Georgia, for a potential data center project, spending about $58.5 million. The land was previously tied to Cloverleaf Infrastructure’s Rumble Technology Campus and approved for 12 data center buildings. While no timeline has been announced, the acquisition reinforces Google’s growing footprint in Georgia’s data infrastructure landscape.
10/10/2025
Vantage TX2 Campus
Vantage Data Centers • TX
Vantage Data Centers has filed a permit for a 214,500-SF, two-story expansion at its TX2 campus in San Antonio, where the first building broke ground in 2023. Construction on this new phase begins October 2025 and is scheduled for completion by mid-2027.
10/10/2025
Hostess Manufacturing Plant Expansion
The J.M. Smucker Company • GA
J.M. Smucker is investing $120M to expand its Hostess plant in Columbus, GA, adding new capacity and equipment. The project, expected to wrap up in 2027, will create 50 jobs and boost the company’s production network.
10/9/2025
Virginia, ClearArc Campus
CleanArc Data Centers • VA
CleanArc Data Centers has acquired more land in Caroline County, Virginia, expanding its debut site to 900 MW of planned capacity. The company targets 2027 for first power, followed by two more 300 MW phases in 2030 and 2033–2035.
10/9/2025
Anthony Township Data Center
Talen Energy Corporation • PA
Talen Energy has requested the rezoning of 1,300 acres in Montour County, Pennsylvania, from agricultural and public use to industrial for potential data center and power projects. While the company already hosts Amazon’s data center at its Cumulus Campus in nearby Berwick, the new rezoning proposal marks an early step in broadening Talen’s energy-linked digital infrastructure footprint across the region. It remains unclear whether the new site would be colocated with power generation.
10/9/2025
Prometheus Casper Campus
Prometheus Hyperscale • WY
Prometheus Hyperscale is developing its second AI data center campus in Wyoming, a project near Casper that could reach 1.5 GW of capacity. An initial $500 million investment will kick-start the build, with first power expected in 2026. Though powered by natural gas, the campus aims to be carbon negative through carbon capture partnerships with Spiritus and Casper Carbon Capture.
10/9/2025
Apple Valley 84
Covington Development Partners • CA
Apple Valley 84 is a newly proposed 1.38 million square foot warehouse and logistics center set to rise on 93 acres near I-15. Designed for modern fulfillment operations with office and cold storage, the project aims to bring major infrastructure upgrades and create over 1,100 jobs in Apple Valley.
10/9/2025
Paso del Norte Industrial Park
CBRE • TX
An 802,000 square feet industrial campus is taking shape near the Zaragoza Port of Entry in El Paso, designed for large-scale logistics and assembly tenants. With direct border access, advanced power infrastructure, and fenced truck courts, the site offers significant operational and drayage cost advantages for binational trade users.
10/9/2025
BREI Solar Farm
Butte Renewable Energy Inc. • CA
BREI plans to develop a utility-scale solar and battery storage facility spanning 116 acres in Oroville, CA, partly located on the former Koppers Superfund site. The unmanned installation will feed clean energy into the PG&E grid, advancing California’s decarbonization targets.
10/9/2025
Eli Lilly Houston Manufacturing Facility
Eli Lilly and Company • TX
Eli Lilly has selected Houston for a $6.5 billion pharma manufacturing complex, marking Texas’ first large-scale biopharma production site. The project will generate thousands of jobs and is slated to come online in five years, signaling Houston’s growing role in advanced manufacturing.
10/9/2025
Google Linn County Campus
Google • IA
Google is signaling a major move: it’s evaluating up to six new data centers in Linn County, Iowa, and has already commissioned a water-usage study to lay the groundwork. The plan aligns with its prior $7 billion investment in Iowa infrastructure. While still in preliminary stages and without a timeline, this speaks to serious intent to deepen its Midwest presence.
10/9/2025
St. Joseph, AWS Campus
Amazon AWS • IN
AWS has confirmed that 7 of 18 buildings from Phase 1 of its Project Rainer–St. Joseph campus are now active, with Phase 2 construction underway. The full development spans 30 buildings totaling 2.2 GW, and Aterio estimates the site will reach 1 GW of active capacity by the end of 2025.
10/31/2025
Future Capacity
Amazon AWS • TX
Amazon’s AWS added 3.8 GW of new capacity over the past year and plans to double its data center footprint within two years, supported by a $125B capex budget for 2025 with additional increases planned for 2026. On the latest earnings call, AWS projected over 1 GW of new capacity activations in Q4 2025, compared to Aterio’s estimate of roughly 1.3 GW.
10/31/2025
OpenAI Stargate - Michigan Campus
Oracle • MI
Following several rezoning rejections, OpenAI, Oracle, and Related Digital have confirmed plans for the Stargate Campus in Benton, Michigan, a 1.5 million sq ft, 1 GW+ AI-focused data center development. The project is slated for activation by Q4 2027, and follows OpenAI’s recent wave of five new campus announcements across the U.S.
10/31/2025
DeForest Campus
QTS Data Centers • WI
QTS Data Centers has initiated discussions with the Village of DeForest about annexing land for a proposed multibillion dollar data center campus; the company plans to submit a zoning application in November.
10/31/2025
Grayslake, T5 Campus
T5 Data Centers • IL
T5 Data Centers has begun construction on its 1.2 GW Chicago IV campus, located in Northlake, Illinois. Satellite imagery from Oct 26, 2025 confirms land grading activity across multiple parcels, with at least three building pads visible. The first facility is scheduled to become operational by 2027
10/31/2025
Wisconsin 1, Microsoft Campus
Microsoft • WI
Microsoft plans to double its data center footprint within two years and expand AI capacity by over 80% in fiscal 2026, responding to surging demand for AI services. The company spent a record $34.9B in Q1 FY2026 capex, including $11.1B in data center leases, announced its 2 GW Fairwater facility in Wisconsin, and deployed its first large-scale NVIDIA GB300 cluster, as Azure grew 40% year-over-year despite ongoing capacity constraints.
10/31/2025
ACG Conyers Manufacturing Facility
ACG • GA
ACG is investing $200 million to establish its first U.S. capsule manufacturing facility in Conyers, Georgia. The state-of-the-art plant will create over 200 jobs and is slated to begin operations by early 2027.
10/30/2025
Good Samaritan Hospital San Jose
HCA Healthcare • CA
HCA Healthcare’s (HCA) Good Samaritan Hospital in San Jose, CA, has broken ground on a $1.3 billion campus expansion. The redevelopment will add a new 715,000 sq. ft. medical center with 234 private patient rooms, upgrading facilities to modern standards.
10/30/2025
Loxley Logistics Center
Crown West Realty • AL
Crown West Realty broke ground on the first building at Loxley Logistics Center, a new 200-acre industrial park in Baldwin County, Alabama. The initial 162,000 sq. ft. cross-dock warehouse will be delivered by late 2026, positioning Loxley as a rising logistics hub on the Gulf Coast
10/30/2025
Hermitage Logistics Hub
Lovett Industrial • TN
Lovett Industrial broke ground on the Hermitage Logistics Hub near Nashville, TN, a 213,840 sq ft Class A warehouse on a 52-acre site. The rear-load facility is scheduled for completion by Q4 2026 to serve rising logistics demand in the growing Nashville market
10/30/2025
Electrolux Kinston Expansion
Electrolux Consumer Products • NC
Electrolux is expanding its Kinston, NC manufacturing plant with a $23.7 million investment. The project will add 30,000 sq. ft. of manufacturing space and create 74 new jobs as the facility ramps up production of stainless steel tub dishwashers
10/30/2025
Georgia 2, Microsoft Campus
Microsoft • GA
New developments spotted at Microsoft’s Georgia 2 Campus in Palmetto, three additional data center buildings have been identified through recent satellite imagery and confirmed by the traffic study for the Microsoft CCO06 Data Center.
10/24/2025
Talkington Campus
CyrusOne • IL
CyrusOne plans a $500 million, 280-acre data center campus in Sangamon County, Illinois, featuring six 250,000 sqft buildings and 600 MW power demand, with construction expected to start in 2026 and completion in 2027.
10/22/2025
Merck Virginia Manufacturing Facility
Merck & Co., Inc. • VA
Merck has broken ground on a $3B, 400,000-sq-ft pharmaceutical manufacturing facility in Elkton, VA, expected to create 8,000 construction jobs and 500 permanent roles upon completion.
10/22/2025
Carolina Renewable Orangeburg Facility
Carolina Renewable Products • SC
Carolina Renewable Products is developing a $280 million renewable diesel and biochar plant in Orangeburg County, South Carolina, creating 155 jobs. The facility will convert sustainable wood biomass into renewable diesel, biochar, and wood vinegar, serving as the company’s headquarters and training hub. Operations are expected to begin in late 2026.
10/22/2025
Morgan County Campus
Google • IN
The 390-acre, four-building data center campus in Morgan County, Indiana has now been confirmed to be developed by Google. Aterio captured the project in February, when early rezoning filings were in process, and Google’s involvement was identified well before the county’s official confirmation this week.
10/22/2025
Project Horizon
CoreWeave • TX
Poolside and CoreWeave are jointly developing Project Horizon, a 2-gigawatt AI campus in Pecos County, Texas, designed for frontier-scale model training. The site will be powered by on-site natural-gas turbines with grid-redundant backup and battery storage, developed in eight 250-megawatt phases, with the first phase scheduled to go live in 2027.
10/22/2025
Project Skyway
Ryan Companies • MN
Ryan Companies has proposed Project Skyway, a 482-acre data center campus in Pine Island, Minnesota, totaling about 3 million sqft across up to three stories. Development applications are expected by late 2025, with power supplied by Xcel Energy.
10/22/2025
Ahold Delhaize Burlington Distribution Center
Ahold Delhaize USA • NC
Ahold Delhaize USA plans a $860M, 1M sq ft automated distribution center in Burlington, NC, supporting Food Lion and other grocery brands, with construction starting 2026 and operations in 2029.
10/22/2025
Atlas Argo Campus
Atlas Agro • WA
Atlas Agro has proposed a five-building data center campus in Richland, Washington, each 500,000 sq ft. Construction is expected to begin in 2027 near the company’s planned green fertilizer plant.
10/22/2025
Amazon Naugatuck Fulfillment Center
Amazon • CT
Amazon has broken ground on a 3.2M sqft robotics fulfillment center on the Waterbury-Naugatuck line, slated to open in 2027 and create 1,000 full-time jobs.
10/22/2025
Averitt Express Mississippi Expansion
Averitt Express • MS
Rankin County is set for growth as Averitt Express expands with a 150,000 sqft logistics hub, promising fresh jobs and a boost to Mississippi’s supply chain sector with a $9.6 million investment.
10/20/2025
Lupin Coral Springs Manufacturing Facility
Lupin Limited • FL
Lupin is establishing a $250M, 70,000-SF pharma facility in Coral Springs, Florida, to manufacture respiratory drugs for U.S. patients. The project will create 200 jobs by 2030 and bolster domestic pharmaceutical production.
10/17/2025
Aligned Frederick Campus
Aligned Data Centers • MD
Aligned Data Centers has begun construction on three additional buildings totaling 1,149,000 sq ft at its Frederick, Maryland campus. These new facilities, approved in May 2025, expand the site to a total of four buildings with a combined planned capacity of 264 MW.
10/16/2025
El Paso, Meta Campus
Facebook • TX
Meta has broken ground on its third Texas data campus in El Paso, investing $1.5 billion for a new AI-driven development. The campus spans 1,000 acres and is scalable to 1 gigawatt, highlighting Meta’s commitment to expanding tech infrastructure across West Texas.
10/16/2025
Energy Way Industrial Park Campus
Amazon AWS • NC
Amazon is launching a $10 billion AI/cloud campus in Richmond County, NC, located next to Duke Energy’s Sherwood H. Smith Jr. energy complex, a gas-fired plant with capacity exceeding 1,200 MW . The development, planned on roughly 800 acres in Energy Way Industrial Park, will feature 20 data center buildings, each about 200,000 to 250,000 sq ft . Satellite imagery from Oct 14, 2025 confirms large-scale site clearing began Oct 1, marking the commencement of groundwork for one of North Carolina’s most ambitious tech infrastructure projects.
10/15/2025
AWS Mattameade Campus
Amazon AWS • VA
Satellite imagery from October 9, 2025 confirms construction has begun on a new 770 MW data center campus, with site clearing underway for Buildings 1 and 2 and advanced concrete work visible at the planned substation. The full project is slated to deliver 770 MW of capacity by 2027.
10/15/2025
Kimberly-Clark Warren Distribution Center
Kimberly-Clark Corporation • OH
Kimberly-Clark (KMB) plans a $160 million, 500,000-SF distribution center beside its upcoming $800 million Warren manufacturing plant, set to break ground in early 2026 and create 65 new jobs.
10/15/2025
Stafford Technology Campus
STACK Infrastructure • VA
STACK Infrastructure has begun construction on its 1 GW+ Stafford Technology Campus at 196–344 Eskimo Hill Rd, Stafford, VA, planned to include 19 buildings totaling 5.8 M sq ft. Satellite imagery from Oct 9, 2025 confirms site grading completed with a defined building pad and perimeter access roads for the first building, while site clearing is underway for the second. The campus will draw committed power from six 300 MW substations supplied by Dominion Energy, positioning it among the largest planned data center developments in Virginia.
10/14/2025
HyperGrid Data Center Campus
FERMI America • TX
Satellite imagery from October 11, 2025 confirms site clearing activity underway at Power Blocks A and B of Project Matador, which began during the fourth week of September. These two blocks will host six (6) 6-on-1 combined-cycle generator configurations using Siemens Energy SGT-800 turbines, representing the first phase of the development. At full operation, this phase is expected to provide approximately 2.25 - 2.5 GW of nameplate capacity, almost a quarter of the project’s planned 11,000 MW total.
10/14/2025
Central Pike Logistics Center
Stream Realty Partners • TN
Stream Realty Partners has begun construction on the 1.1 million square-foot Central Pike Logistics Center in Lebanon, Tennessee, marking its first industrial project in the Nashville market. The two-building speculative development spans 89 acres, with Cushman & Wakefield overseeing leasing and Mycon Construction as the general contractor.
10/14/2025
Canton, AWS Campus
Amazon AWS • MS
Satellite imagery from October 4, 2025 confirms large-scale land grading on five additional data centers at AWS's Canton campus. The site currently hosts one active facility, with four in advanced construction expected to come online by Q4 2025. The full master plan includes up to 16 buildings spread across 927 acres. For this campus AWS operates under long-term Power Purchase Agreements (PPAs) with Entergy, securing renewable energy, primarily sola, to supply the site through dedicated grid infrastructure.
10/10/2025
Charleston Aerospace Facility
Eaton • SC
Eaton (ETN) is investing $46 million to build a new aerospace manufacturing facility next to its North Charleston site, creating over 50 jobs. The plant will handle machining, additive manufacturing, and hydraulic system testing, with operations expected to begin in 2028.
10/10/2025
Rumble Technology Campus
Google • GA
Google has purchased 950 acres in Monroe County, Georgia, for a potential data center project, spending about $58.5 million. The land was previously tied to Cloverleaf Infrastructure’s Rumble Technology Campus and approved for 12 data center buildings. While no timeline has been announced, the acquisition reinforces Google’s growing footprint in Georgia’s data infrastructure landscape.
10/10/2025
Vantage TX2 Campus
Vantage Data Centers • TX
Vantage Data Centers has filed a permit for a 214,500-SF, two-story expansion at its TX2 campus in San Antonio, where the first building broke ground in 2023. Construction on this new phase begins October 2025 and is scheduled for completion by mid-2027.
10/10/2025
Hostess Manufacturing Plant Expansion
The J.M. Smucker Company • GA
J.M. Smucker is investing $120M to expand its Hostess plant in Columbus, GA, adding new capacity and equipment. The project, expected to wrap up in 2027, will create 50 jobs and boost the company’s production network.
10/9/2025
Virginia, ClearArc Campus
CleanArc Data Centers • VA
CleanArc Data Centers has acquired more land in Caroline County, Virginia, expanding its debut site to 900 MW of planned capacity. The company targets 2027 for first power, followed by two more 300 MW phases in 2030 and 2033–2035.
10/9/2025
Anthony Township Data Center
Talen Energy Corporation • PA
Talen Energy has requested the rezoning of 1,300 acres in Montour County, Pennsylvania, from agricultural and public use to industrial for potential data center and power projects. While the company already hosts Amazon’s data center at its Cumulus Campus in nearby Berwick, the new rezoning proposal marks an early step in broadening Talen’s energy-linked digital infrastructure footprint across the region. It remains unclear whether the new site would be colocated with power generation.
10/9/2025
Prometheus Casper Campus
Prometheus Hyperscale • WY
Prometheus Hyperscale is developing its second AI data center campus in Wyoming, a project near Casper that could reach 1.5 GW of capacity. An initial $500 million investment will kick-start the build, with first power expected in 2026. Though powered by natural gas, the campus aims to be carbon negative through carbon capture partnerships with Spiritus and Casper Carbon Capture.
10/9/2025
Apple Valley 84
Covington Development Partners • CA
Apple Valley 84 is a newly proposed 1.38 million square foot warehouse and logistics center set to rise on 93 acres near I-15. Designed for modern fulfillment operations with office and cold storage, the project aims to bring major infrastructure upgrades and create over 1,100 jobs in Apple Valley.
10/9/2025
Paso del Norte Industrial Park
CBRE • TX
An 802,000 square feet industrial campus is taking shape near the Zaragoza Port of Entry in El Paso, designed for large-scale logistics and assembly tenants. With direct border access, advanced power infrastructure, and fenced truck courts, the site offers significant operational and drayage cost advantages for binational trade users.
10/9/2025
BREI Solar Farm
Butte Renewable Energy Inc. • CA
BREI plans to develop a utility-scale solar and battery storage facility spanning 116 acres in Oroville, CA, partly located on the former Koppers Superfund site. The unmanned installation will feed clean energy into the PG&E grid, advancing California’s decarbonization targets.
10/9/2025
Eli Lilly Houston Manufacturing Facility
Eli Lilly and Company • TX
Eli Lilly has selected Houston for a $6.5 billion pharma manufacturing complex, marking Texas’ first large-scale biopharma production site. The project will generate thousands of jobs and is slated to come online in five years, signaling Houston’s growing role in advanced manufacturing.
10/9/2025
Google Linn County Campus
Google • IA
Google is signaling a major move: it’s evaluating up to six new data centers in Linn County, Iowa, and has already commissioned a water-usage study to lay the groundwork. The plan aligns with its prior $7 billion investment in Iowa infrastructure. While still in preliminary stages and without a timeline, this speaks to serious intent to deepen its Midwest presence.