In Just Two Weeks, Local Pushback Halts 2.3GW of Amazon Data Center Projects

Aterio Research Team

Within just two weeks, Amazon canceled two of its ambitious U.S. data center projects: one in Virginia and the other in Arizona. Together, the canceled plans would have added more than 9.7 million square feet of space and 2.37 gigawatts of power capacity.
These weren’t speculative ideas. Both had already progressed into public hearings and partnerships. But by July 24 (Virginia) and August 7 (Arizona), both were off the table. The takeaway is simple: local pushback and resource pressures can stall even large, well-financed builds.
Virginia: A 7.2M Sq Ft Campus Halted by Local Resistance
In Louisa County, VA, Amazon had proposed its third campus in the Technology Overlay District (TOD), spanning 1,370 acres and offering up to 1,742 MW of data center capacity based on Aterio's estimates.
But during a heated public meeting in June, residents voiced concerns over 24/7 operational noise, infrastructure strain, and rural quality of life. Less than a month later, on July 24, 2025, Amazon withdrew the application, despite the project being located in a pre-zoned tech district.
This case underscores how Conditional Use Permits (CUPs) and community engagement rules can override land use expectations, even in areas designed for tech development.
Arizona: Project Blue Denied Over Water and Transparency
Barely two weeks later, on August 7, the Tucson City Council unanimously rejected Project Blue, a 630 MW campus backed by Beale Infrastructure and Blue Owl Capital. Although initially kept confidential, it was recently revealed that AWS was the company behind the project, intensifying public scrutiny.
The project, planned for 290 acres in southern Tucson, sparked opposition over excessive water demand, lack of transparency, and concern about annexation procedures.
Despite offering $3.6 billion in investment and hundreds of jobs, the backlash proved insurmountable. Critics pointed out that Project Blue’s full buildout would require 1,910 acre-feet of water annually, more than any current local utility customer.
Two Projects. Two Weeks.
What ties these back-to-back cancellations together?
- Both projects were deeply embedded in zoned or incentivized geographies
- Both involved partnerships with established developers and infrastructure funds
- Both were derailed not by federal regulators or capital constraints, but by hyperlocal opposition
Together, they represent:
- 2.37 GW of lost future capacity in the region
- $10B+ in shelved investment
Headlines aside, these cancellations are not definitive. With grid constraints and lengthy queues, hyperscalers commonly advance multiple sites concurrently, fully aware that some will stall or be withdrawn. Applications can be amended, shifted to adjacent parcels, or resubmitted under different terms. The underlying signal is clear: demand for capacity is still surging, and large pools of capital remain committed.
How Aterio Helps You Get Ahead
At Aterio, we track permits, filings, and withdrawals nationwide, spotting early friction like rejected applications and stalled approvals, as well as greenlights on new projects. From shifting local rules to sudden surges in activity, we surface the signals that shape infrastructure timelines before they hit the headlines.
Use our data to:
- Track campus-level trends before announcements make headlines
- Track construction progress monitored with satellite images
- Identify new projects throughout the US
Download our August Report or schedule a call.