In Just Two Weeks, Local Pushback Halts 2.3GW of Amazon Data Center Projects

Aterio Research Team

Aterio Research Team

Research at Aterio

amazon_cancelled_data_centers

Within just two weeks, Amazon canceled two of its ambitious U.S. data center projects: one in Virginia and the other in Arizona. Together, the canceled plans would have added more than 9.7 million square feet of space and 2.37 gigawatts of power capacity.

Aterio datasets

See the data behind the story

The records behind this article live in the US Data Center Locations and Power Demand dataset.

These weren’t speculative ideas. Both had already progressed into public hearings and partnerships. But by July 24 (Virginia) and August 7 (Arizona), both were off the table. The takeaway is simple: local pushback and resource pressures can stall even large, well-financed builds.

Virginia: A 7.2M Sq Ft Campus Halted by Local Resistance

In Louisa County, VA, Amazon had proposed its third campus in the Technology Overlay District (TOD), spanning 1,370 acres and offering up to 1,742 MW of data center capacity based on Aterio's estimates.


But during a heated public meeting in June, residents voiced concerns over 24/7 operational noise, infrastructure strain, and rural quality of life. Less than a month later, on July 24, 2025, Amazon withdrew the application, despite the project being located in a pre-zoned tech district.

This case underscores how Conditional Use Permits (CUPs) and community engagement rules can override land use expectations, even in areas designed for tech development.

Arizona: Project Blue Denied Over Water and Transparency

Barely two weeks later, on August 7, the Tucson City Council unanimously rejected Project Blue, a 630 MW campus backed by Beale Infrastructure and Blue Owl Capital. Although initially kept confidential, it was recently revealed that AWS was the company behind the project, intensifying public scrutiny.

The project, planned for 290 acres in southern Tucson, sparked opposition over excessive water demand, lack of transparency, and concern about annexation procedures.

Despite offering $3.6 billion in investment and hundreds of jobs, the backlash proved insurmountable. Critics pointed out that Project Blue’s full buildout would require 1,910 acre-feet of water annually, more than any current local utility customer.

Two Projects. Two Weeks.

What ties these back-to-back cancellations together?

  • Both projects were deeply embedded in zoned or incentivized geographies
  • Both involved partnerships with established developers and infrastructure funds
  • Both were derailed not by federal regulators or capital constraints, but by hyperlocal opposition

Together, they represent:

  • 2.37 GW of lost future capacity in the region
  • $10B+ in shelved investment

Headlines aside, these cancellations are not definitive. With grid constraints and lengthy queues, hyperscalers commonly advance multiple sites concurrently, fully aware that some will stall or be withdrawn. Applications can be amended, shifted to adjacent parcels, or resubmitted under different terms. The underlying signal is clear: demand for capacity is still surging, and large pools of capital remain committed.

How Aterio Helps You Get Ahead


At Aterio, we track permits, filings, and withdrawals nationwide, spotting early friction like rejected applications and stalled approvals, as well as greenlights on new projects. From shifting local rules to sudden surges in activity, we surface the signals that shape infrastructure timelines before they hit the headlines.


Use our data to:

  • Track campus-level trends before announcements make headlines
  • Track construction progress monitored with satellite images
  • Identify new projects throughout the US

Download our August Report or schedule a call.

Keep reading

Satellite view of the former Portsmouth Gaseous Diffusion Plant in Piketon, Ohio on June 24, 2026: the large white process buildings and paved yards of the existing plant at left, ringed by a perimeter road, with farmland, woodland and open fields covering the surrounding acreage where the PORTS Technology Campus is planned.

SB Energy's 10 GW Ohio Campus Is Raising Capital Faster Than It Is Moving Dirt

SB Energy's 10 GW Piketon campus has a $250B Nvidia backstop in talks and no visible construction since its March groundbreaking.

Juan Felipe Hernandez

Juan Felipe Hernandez

Data Center Analyst at aterio.io

Site construction plan from the TSMC Arizona CHIPS Act Draft Environmental Assessment: the 1,129-acre north Phoenix campus outlined in red along Loop 303 and West Carefree Highway, with fab buildings F21P1, F21P2 and F21P3 and support buildings outlined in purple, and a parking area marked for solar panels

TSMC's $265 Billion Arizona Gigafab: Three Fabs You Can See, Seven on Paper

TSMC's Arizona gigafab is now a $265 billion commitment, but just three of the ten announced fabs show construction on the ground.

Fayad Chowdhury

Fayad Chowdhury

Industrial Developments Analyst at aterio.io

Aerial view of a Microsoft data center campus surrounded by farmland, with rows of low white server buildings, backup generator yards and electrical substations under a cloudy sky.

Microsoft Restarts the Three Ohio Campuses It Cancelled in 2025, Roughly 869 MW

Microsoft cancelled roughly 869 MW of Ohio data center capacity in April 2025, and all three Licking County campuses are now grading toward a 2029 target.

Javier Reyes

Javier Reyes

Data Analyst at aterio.io