In Just Two Weeks, Local Pushback Halts 2.3GW of Amazon Data Center Projects

Aterio Research Team

Research at Aterio

amazon_cancelled_data_centers

Within just two weeks, Amazon canceled two of its ambitious U.S. data center projects: one in Virginia and the other in Arizona. Together, the canceled plans would have added more than 9.7 million square feet of space and 2.37 gigawatts of power capacity.

Aterio datasets

See the data behind the story

The records behind this article live in the US Data Center Database: Locations and Power Demand dataset.

These weren’t speculative ideas. Both had already progressed into public hearings and partnerships. But by July 24 (Virginia) and August 7 (Arizona), both were off the table. The takeaway is simple: local pushback and resource pressures can stall even large, well-financed builds.

Virginia: A 7.2M Sq Ft Campus Halted by Local Resistance

In Louisa County, VA, Amazon had proposed its third campus in the Technology Overlay District (TOD), spanning 1,370 acres and offering up to 1,742 MW of data center capacity based on Aterio's estimates.


But during a heated public meeting in June, residents voiced concerns over 24/7 operational noise, infrastructure strain, and rural quality of life. Less than a month later, on July 24, 2025, Amazon withdrew the application, despite the project being located in a pre-zoned tech district.

This case underscores how Conditional Use Permits (CUPs) and community engagement rules can override land use expectations, even in areas designed for tech development.

Arizona: Project Blue Denied Over Water and Transparency

Barely two weeks later, on August 7, the Tucson City Council unanimously rejected Project Blue, a 630 MW campus backed by Beale Infrastructure and Blue Owl Capital. Although initially kept confidential, it was recently revealed that AWS was the company behind the project, intensifying public scrutiny.

The project, planned for 290 acres in southern Tucson, sparked opposition over excessive water demand, lack of transparency, and concern about annexation procedures.

Despite offering $3.6 billion in investment and hundreds of jobs, the backlash proved insurmountable. Critics pointed out that Project Blue’s full buildout would require 1,910 acre-feet of water annually, more than any current local utility customer.

Two Projects. Two Weeks.

What ties these back-to-back cancellations together?

  • Both projects were deeply embedded in zoned or incentivized geographies
  • Both involved partnerships with established developers and infrastructure funds
  • Both were derailed not by federal regulators or capital constraints, but by hyperlocal opposition

Together, they represent:

  • 2.37 GW of lost future capacity in the region
  • $10B+ in shelved investment

Headlines aside, these cancellations are not definitive. With grid constraints and lengthy queues, hyperscalers commonly advance multiple sites concurrently, fully aware that some will stall or be withdrawn. Applications can be amended, shifted to adjacent parcels, or resubmitted under different terms. The underlying signal is clear: demand for capacity is still surging, and large pools of capital remain committed.

How Aterio Helps You Get Ahead


At Aterio, we track permits, filings, and withdrawals nationwide, spotting early friction like rejected applications and stalled approvals, as well as greenlights on new projects. From shifting local rules to sudden surges in activity, we surface the signals that shape infrastructure timelines before they hit the headlines.


Use our data to:

  • Track campus-level trends before announcements make headlines
  • Track construction progress monitored with satellite images
  • Identify new projects throughout the US

Download our August Report or schedule a call.

Keep reading

Side by side satellite views of PORTS Technology Campus Phase 1 in Pike County, Ohio, on October 27 and November 10, 2026, with the West and East building footprints from the site plan overlaid. The November view shows newly cleared ground near both footprints.

PORTS Technology Campus: Dirt Is Moving

Site clearing has started near the first two PORTS buildings in Pike County, Ohio. We estimate 900 to 944 MW of IT capacity across them, with first power expected in 2028.

Aterio Research Team

Research at Aterio

Tombstone Resources concept plan for the AEPCO parcels of Cochise Supercomputer Campus: five 700 MW computing buildings in two groups, with dry coolers, Megapacks and a detention facility

November 4 Findings: SpaceX-Linked 6 GW Campus in Cochise County, Arizona Targets Initial 1.5 GW by 2027

Tombstone Resources has filed for Cochise Supercomputer Campus in Arizona, with SpaceX named as town hall host: 1.5 GW of initial demand, rising to 6 GW at full build out.

Aterio Research Team

Research at Aterio

Optical and thermal aerial views of IREN's Childress campus in Texas, 21 October 2026

Aterio Identifies Potential Horizon 4 Delivery Risk

Our 21 October flyover puts Horizon 4 roughly where Horizon 3 was in late July. Horizons 2 and 3 look on track for Q4 2026; Horizon 4 risks slipping to Q1 2027.

Data Center Research Team

Research at Aterio