Tarboro's 'Net Zero' Data Center Runs on Gas, and the Town Voted It Down 7-1

Caio Cunha

Energy Analyst at Aterio

Site plan of the Tarboro Net Zero data center campus on aerial imagery, off Anaconda Road in Tarboro, North Carolina, showing the project area with two buildings, a chiller yard, an on-site generation yard, a BESS yard, and the Tarboro electric substation.

Key takeaways

  • The Tarboro Net Zero Data Center Campus is a $6.4 billion, behind-the-meter data center proposed by Energy Storage Solutions, LLC on roughly 52 acres off Anaconda Road in Tarboro, Edgecombe County, North Carolina.
  • The campus's "Net Zero" label refers to an unproven "Carbon Sponge" CO2-capture system bolted onto on-site natural gas and hydrogen generation, not solar: Energy Storage Solutions pledged about $100 million to it and conceded that no data center currently uses the technology.
  • The project pairs on-site natural gas (and hydrogen) generation (22 gas units at 3.3 MW, 72.6 MW in the town zoning filing) with a solid-state graphene battery that grew from 250 MW / 1.0 GWh to 300 MW / 1.2 GWh between June and August 2025, all behind the meter.
  • Tarboro's Town Council denied the project's Special Use Permit 7-1 on September 8, 2025, finding it would endanger public health and injure neighboring property values, that natural gas supply was not assured, and that the carbon capture was unproven; the project is now recorded as not approved, and Energy Storage Solutions has filed a Superior Court appeal (case 25CV004521-320).
  • The estimated cost rose from $1.29 billion in June 2025 to $6.4 billion by August 2025; a separate, larger Energy Storage Solutions project, the roughly $19 billion Kingsboro data center in unincorporated Edgecombe County, is a distinct campus that would sell power to the grid.

Aterio datasets

See the data behind the story

The records behind this article live in the US Data Center Locations and Power Demand dataset.

Aterio's review of the Edgecombe County zoning filings for the Tarboro campus, which its developer bills as a "Net Zero" data center, shows what that label actually covers: not a solar farm, but on-site natural gas and hydrogen generation paired with a solid-state graphene battery and an unproven "Carbon Sponge" meant to capture 130 percent of the plant's emissions. The behind-the-meter campus, sized around 72.6 MW of gas generation and a 300 MW / 1.2 GWh battery on a roughly 52-acre site off Anaconda Road, carried a $6.4 billion price tag by August 2025.

The design is a genuine attempt to self-power an AI data center without the grid, and to bolt a carbon-capture answer onto the gas that makes it possible. The catch is that the centerpiece of the "Net Zero" claim is a technology the developer admits no data center has ever used, the capacity figures on file swing widely, the cost quintupled in two months, and on September 8, 2025 the Tarboro Town Council rejected the permit 7-1. Energy Storage Solutions has since appealed to the Edgecombe County Superior Court.

Site plan of the Tarboro Net Zero data center campus overlaid on aerial imagery, showing the roughly 13.8-acre project area off Anaconda Road in Tarboro, North Carolina, with two proposed buildings, a chiller yard, an on-site generation yard, a BESS yard, the 2.5-acre Tarboro electric substation, and a detention pond within a 52-acre total site bounded by I-2 and AR-20 zoning

Figure: The Tarboro Net Zero campus site plan, a roughly 13.8-acre project area on the 52-acre Anaconda Road site, pairing two data-center buildings and a chiller yard with an on-site natural gas generation yard, a BESS yard, and the 2.5-acre Tarboro electric substation. Source: Tarboro zoning agenda, August 18, 2025 (p. 105).

What "Net Zero" actually means here

There is no solar plant at Tarboro. In its Special Use Permit application, Energy Storage Solutions describes the green claim in its own words: "we will use cogeneration and a 'carbon sponge' clean energy system to capture 130 percent of the CO2 and other emissions as a 'green sequestration' system." The power underneath that sentence is natural gas (the Town's order notes the plant would also burn hydrogen). The "Net Zero" is a capture-and-credit layer on top of a gas plant: a company representative told My Tarboro Today the campus could claim a federal carbon-capture tax credit of up to $280 per ton.

The developer has been candid that the centerpiece is untested. "We are not aware of any data centers using this new technology involved with the Carbon Sponge system," a company representative told My Tarboro Today, adding that Energy Storage Solutions would "provide approximately $100 million to clean up the pollution at the campus by using this system." A $100 million bet on a first-of-its-kind capture system is the entire distance between "gas plant" and "Net Zero data center."

The 'Net Zero' is a carbon sponge on a gas plant
How Energy Storage Solutions describes reaching 'Net Zero' at Tarboro: on-site natural gas and hydrogen generation, whose gas-combustion emissions feed an unproven 'Carbon Sponge' system the developer says captures 130 percent of them, positioning the campus for federal carbon-capture credits. There is no on-site solar plant.
The 'Net Zero' is a carbon sponge on a gas plantGas + hydrogen generation (No on-site solar) -> CO2 + emissions (From gas combustion) -> 'Carbon Sponge' capture (Claims 130%, unproven) -> Carbon credits = 'Net Zero' (~$100M pledged)Gas + hydrogengenerationNo on-site solarCO2 +emissionsFrom gas combustion'CarbonSponge' captureClaims 130%, unprovenCarbon credits= 'Net Zero'~$100M pledged
How Energy Storage Solutions describes reaching 'Net Zero' at Tarboro: on-site natural gas and hydrogen generation, whose gas-combustion emissions feed an unproven 'Carbon Sponge' system the developer says captures 130 percent of them, positioning the campus for federal carbon-capture credits. There is no on-site solar plant.

Two on-site plants, sizes that keep moving

The campus is two behind-the-meter plants at one address. The first is on-site power generation: the Tarboro zoning agenda lists 22 gas units of 3.3 MW each, 72.6 MW in total, and the Town's denial order describes the plant as burning both natural gas and hydrogen. The second is a solid-state graphene battery that scaled as the project moved through review, from 250 MW / 1.0 GWh in the June 16, 2025 Planning Board materials to 300 MW / 1.2 GWh by the August-to-September 2025 permit hearing.

Detailed site plan of the Tarboro Net Zero project area showing two proposed 39,960-square-foot data-center buildings flanking a central chiller yard, a BESS yard, and an on-site natural gas generation yard, with the 2.5-acre Tarboro electric substation to the southeast and loading docks, a security fence, and a gas line marked

Figure: The project-area layout: two 39,960-square-foot buildings flank the chiller yard and BESS yard, with the on-site natural gas generation yard at center and the 2.5-acre Tarboro electric substation to the southeast. Source: Tarboro zoning agenda, August 18, 2025 (p. 104).

The public record around the campus is also easy to get wrong. A 900 MW figure that appears in some coverage is not this project at all: it belongs to Energy Storage Solutions' separate, larger Kingsboro data center in unincorporated Edgecombe County, a roughly $19 billion campus that would sell power to the grid. Even this campus's own size moved as it went, the battery scaling up and the price more than quintupling between the June hearing and the September vote. The Anaconda Road "Net Zero" campus is the smaller, behind-the-meter one the town turned down.

That is exactly what a properly-researched record is for. The public filings for Tarboro shift between the June hearing and the September vote, a press account attaches another project's 900 MW to it, and even the developer's name is recorded three different ways across sources. Aterio's job is to reconcile every filing, permit, and press account for a project into one verified, source-linked record, so the capacity and status an investor or operator acts on are the ones the documents actually support, not whichever figure a single article happened to print.

The price quintupled in two months
The Tarboro Net Zero campus's estimated cost jumped from $1.29 billion, described at the June 2025 Planning Board meeting, to $6.4 billion by the August 2025 permit hearing: nearly a fivefold rise in two months as the full compute build was folded in.
The price quintupled in two monthsJune 2025: $1.29B; Aug 2025: $6.4BJune 2025$1.29BAug 2025$6.4BPEAK AUG 2025 $6.4B
SOURCE: connectcre.com

Key project parameters:

  • Developer: Energy Storage Solutions, LLC (the Special Use Permit applicant); a federal EIA-860M search returns no generator registered to it or to its parent, North Carolina Renewable Energy, LLC, consistent with an off-grid design. Construction is attributed to ARCO Design and Build.
  • Location: a roughly 52-acre site (13.8-acre developed project area) on the south side of Anaconda Road, between McNair Road and Western Boulevard, in Tarboro, Edgecombe County, North Carolina (35.90151, -77.584274).
  • On-site generation: on-site natural gas and hydrogen generation (the Town's denial order names both fuels), with 72.6 MW of gas in the town zoning filing (22 units at 3.3 MW), behind the meter; the "Carbon Sponge" capture on the gas emissions is the "Net Zero" layer.
  • Storage: a solid-state graphene battery system of 300 MW / 1.2 GWh at the August 2025 hearing, up from 250 MW / 1.0 GWh in June 2025.
  • Data-center load: three data centers (two 25 MW units, NetZero 1 and 2, plus a 50 MW NetZero 3 "Mobile"), about 100 MW of initial IT load, for an undisclosed "top tier" tenant.
  • Cost and water: about $6.4 billion (up from $1.29 billion), roughly 500 jobs across six phases, drawing about 2 million gallons of water per day from the Town of Tarboro.

Source: Tarboro zoning agenda, ConnectCRE, and the Aterio U.S. Data Center dataset.

NetZero 3 site plan showing rows of mobile data-center containers beside a BESS yard and an on-site generation yard at the Tarboro Net Zero campus

Figure: The "NetZero 3" site plan, rows of mobile data-center containers beside the BESS yard and the on-site generation yard, the campus's third, containerized data center. Source: Tarboro zoning agenda, August 18, 2025 (p. 96).

Filed, backed, then denied 7-1

The permit path is the clearest part of the record. Energy Storage Solutions filed its Special Use Permit application on April 10, 2025. On June 16, 2025 the Tarboro Planning Board gave the proposal unanimous backing and sent it to the Town Council. By the time the council took it up, the price had grown from the $1.29 billion described at the June Planning Board meeting to $6.4 billion, and the battery had scaled from 250 MW / 1.0 GWh to 300 MW / 1.2 GWh.

Then the local process reversed the momentum. On September 8, 2025 the Tarboro Town Council denied Special Use Permit #25-02 by a 7-1 vote. The council's order found the project would endanger public health through point-source emissions from burning gas, would injure the value of adjoining residential and industrial property, and lacked assured natural gas supply, and it found the "Carbon Sponge" a "novel device" backed by "no data or documentation." The Town denied the permit on "public testimony," even though its own planning staff and Planning Board had recommended approval, its order acknowledged the application complied with the ordinance, and the developer projected $11 million a year in new revenue for the town. Residents had also raised a constant 60-decibel hum and added traffic. Energy Storage Solutions promised an appeal and, on November 13, 2025, filed a petition for writ of certiorari with the Edgecombe County Superior Court (case 25CV004521-320).

Filed milestones in navy; Aterio estimates in amber, dotted with hollow markers.
Project timelineApr 10, 2025: SUP application filed -> Jun 16, 2025: Planning Board backs it, unanimous -> Sep 8, 2025: Town Council denies 7-1 -> Nov 13, 2025: Superior Court appeal filedApr 10, 2025SUP application filedJun 16, 2025Planning Board backs it, unanimousSep 8, 2025Town Council denies 7-1Nov 13, 2025Superior Court appeal filed
The Special Use Permit path for the Tarboro Net Zero campus: filed April 10, 2025, recommended unanimously by the Planning Board on June 16, 2025, and denied 7-1 by the Town Council on September 8, 2025. The project is recorded as not approved; on November 13, 2025 Energy Storage Solutions filed a petition for writ of certiorari with the Edgecombe County Superior Court (case 25CV004521-320).

Bottom line

Tarboro is a test of how far "Net Zero" branding stretches when the generation underneath it is gas. Energy Storage Solutions built a behind-the-meter campus that skips the grid and the interconnection queue, paired 72.6 MW of gas with a 300 MW / 1.2 GWh battery, and staked its green claim on a $100 million capture system it concedes is unproven. A local council looked at the same file, saw a $6.4 billion off-grid gas plant with capacity figures that would not sit still, and voted it down 7-1.

What to watch: the Superior Court appeal (case 25CV004521-320) and whether it revives the denied project; whether Energy Storage Solutions' larger, grid-selling Kingsboro project fares better than its behind-the-meter "Net Zero" one; and whether local permitting bodies elsewhere start treating on-site gas plus carbon capture as the new interconnection fight. Knowing which of those outcomes is real, and which figure on file is the one that holds, is the reason Aterio reconciles every filing and project into one verified record, the same way we tracked the on-site gas-and-battery power stack behind xAI's Colossus 1 and how former bitcoin miners repurposed power-rich sites into AI hosting: the scarce asset is firm power, and the fight is increasingly local.

Frequently asked questions

Why was the Tarboro data center permit denied?

The Tarboro Town Council denied the campus's Special Use Permit 7-1 on September 8, 2025. The council found the gas-burning plant would endanger public health and injure neighboring property values, that natural gas supply was not assured, and that the Carbon Sponge capture system was unproven. Energy Storage Solutions appealed to the Edgecombe County Superior Court on November 13, 2025 (case 25CV004521-320).

Does the Tarboro Net Zero data center use solar power?

No. The Tarboro Net Zero campus has no on-site solar: it pairs 72.6 MW of on-site natural gas and hydrogen generation (22 units of 3.3 MW each) with a 300 MW / 1.2 GWh solid-state graphene battery, all behind the meter. The Net Zero label rests on an unproven Carbon Sponge system the developer says would capture 130 percent of the plant's emissions.

How much will the Tarboro Net Zero data center cost?

The Tarboro Net Zero campus carried an estimated cost of about $6.4 billion by August 2025, up from $1.29 billion in June 2025, nearly a fivefold rise in two months. The developer projected roughly 500 jobs across six phases and about $11 million a year in new town revenue, with the campus drawing about 2 million gallons of water per day.

Who is building the Tarboro data center in North Carolina?

Energy Storage Solutions, LLC is the Special Use Permit applicant for the Tarboro Net Zero campus, a roughly 52-acre site off Anaconda Road in Tarboro, Edgecombe County, with construction attributed to ARCO Design and Build. It is separate from the company's larger Kingsboro data center in unincorporated Edgecombe County, a roughly $19 billion campus that would sell power to the grid.

Aterio tracks U.S. data center and power projects in real time, from early zoning and siting filings to satellite-confirmed construction. Explore Aterio's latest U.S. Data Center Report for state-by-state insights, provider comparisons, and project pipeline analysis, or schedule a call to see how our data can support your investment analysis.

Keep reading

Satellite view of the former Portsmouth Gaseous Diffusion Plant in Piketon, Ohio on June 24, 2026: the large white process buildings and paved yards of the existing plant at left, ringed by a perimeter road, with farmland, woodland and open fields covering the surrounding acreage where the PORTS Technology Campus is planned.

SB Energy's 10 GW Ohio Campus Is Raising Capital Faster Than It Is Moving Dirt

SB Energy's 10 GW Piketon campus has a $250B Nvidia backstop in talks and no visible construction since its March groundbreaking.

Juan Felipe Hernandez

Juan Felipe Hernandez

Data Center Analyst at aterio.io

Aerial view of a Microsoft data center campus surrounded by farmland, with rows of low white server buildings, backup generator yards and electrical substations under a cloudy sky.

Microsoft Restarts the Three Ohio Campuses It Cancelled in 2025, Roughly 869 MW

Microsoft cancelled roughly 869 MW of Ohio data center capacity in April 2025, and all three Licking County campuses are now grading toward a 2029 target.

Javier Reyes

Javier Reyes

Data Analyst at aterio.io

Side-by-side satellite comparison of Microsoft's Boyd Farm data center campus in Catawba County, North Carolina, dated November 11, 2025 and February 10, 2026, with a new electrical substation cluster and freshly graded building pad in the south of the campus circled in the later image

Microsoft Restarts Its Three Paused North Carolina Data Center Campuses, Up to 810 MW

Microsoft's three paused Catawba County data center campuses, up to 810 MW, are moving again, caught by Aterio's satellite imagery in early 2026.

Javier Reyes

Javier Reyes

Data Analyst at aterio.io