Valar Atomics is planning Project Beehive near Wellington, Utah, a data center campus spanning more than 9,000 acres of BLM land. The project includes approximately 9.6 GW of planned onsite nuclear generation from roughly 456 small reactors. BLM is reviewing the application, with non-nuclear construction potentially starting by late 2026, first reactors targeted for 2028, and full buildout by 2032.
There are no events from this company
According to the 2020 US census, the population of Wellington, UT was 1,599.
The forecasted population for Wellington, UT in 2026 is 1,613.
The projected population for Wellington, UT in 2030 is 1,599.
The average household income in Wellington, UT is $52,395.