SpaceX, through Tombstone Resources LLC, is planning the Cochise Supercomputer Campus in Cochise County, AZ, a nine-building data center campus spanning 747 acres with initial demand of 1.5 GW, potentially expanding to 6 GW at full buildout. The project represents up to $50B in investment, with grid power dependent on further studies and agreements with SSVEC and AEPCO. Construction is preliminarily targeted for spring 2027, with a Planning and Zoning hearing scheduled for December 9, 2026.
The average property price in Cochise, AZ is $237,397.
The property prices in Cochise, AZ are currently on an increasing trend.