How much power will data centers in Texas need by 2030?

Sergio Toro

Chief Executive at aterio.io

How much power will data centers in Texas need by 2030?

How much electricity will Texas data centers need by 2030?

Aterio’s latest forecast shows demand climbing from 4.71 GW in 2025 to 12.12 GW in 2030—a 7.41 GW jump in just five years, enough to power roughly 6 million U.S. homes.

Aterio datasets

See the data behind the story

The records behind this article live in the US Data Center Locations and Power Demand dataset.

Why the surge? Texas continues to attract hyperscale and AI‑focused facilities thanks to land availability, robust transmission corridors, competitive power pricing, and a fast‑moving interconnection queue.

And that 12.12 GW figure is conservative. It assumes only 70 % of newly announced projects actually get built. If every announcement on the books today reaches completion, Texas alone would need ~15 GW of new load—more than the peak demand of several U.S. states combined.

How we build it

  • Permits & interconnection filings (state, county, ISO queues)
  • Satellite‑image & aerial updates to confirm construction progress
  • Provider press releases & SEC/PUC submissions
  • Utility resource‑planning docs & PUR filings
  • Daily QA by analysts to reconcile discrepancies (ownership changes, stage slippage, delays)

Dataset size (June 2025)

  • 4,300+ total data‑center buildings in the US
  • 2,300+ announced / under‑construction buildings
  • 350+ projects with generator‑level equipment detail
  • Daily updates + weekly market overview + public monthly report (30‑day lag)

Who uses it?
Grid planners, utilities, OEMs, commodity desks, real‑estate investors—and increasingly AI teams that feed the data directly into LLM‑based agents for automated risk alerts or site scouting.

Texas is just one story. We track every U.S. market—down to which provider is energizing which substation and when.

Texas, US data centers inventory - Aterio

Keep reading

Satellite view of the former Portsmouth Gaseous Diffusion Plant in Piketon, Ohio on June 24, 2026: the large white process buildings and paved yards of the existing plant at left, ringed by a perimeter road, with farmland, woodland and open fields covering the surrounding acreage where the PORTS Technology Campus is planned.

SB Energy's 10 GW Ohio Campus Is Raising Capital Faster Than It Is Moving Dirt

SB Energy's 10 GW Piketon campus has a $250B Nvidia backstop in talks and no visible construction since its March groundbreaking.

Juan Felipe Hernandez

Juan Felipe Hernandez

Data Center Analyst at aterio.io

Site construction plan from the TSMC Arizona CHIPS Act Draft Environmental Assessment: the 1,129-acre north Phoenix campus outlined in red along Loop 303 and West Carefree Highway, with fab buildings F21P1, F21P2 and F21P3 and support buildings outlined in purple, and a parking area marked for solar panels

TSMC's $265 Billion Arizona Gigafab: Three Fabs You Can See, Seven on Paper

TSMC's Arizona gigafab is now a $265 billion commitment, but just three of the ten announced fabs show construction on the ground.

Fayad Chowdhury

Fayad Chowdhury

Industrial Developments Analyst at aterio.io

Aerial view of a Microsoft data center campus surrounded by farmland, with rows of low white server buildings, backup generator yards and electrical substations under a cloudy sky.

Microsoft Restarts the Three Ohio Campuses It Cancelled in 2025, Roughly 869 MW

Microsoft cancelled roughly 869 MW of Ohio data center capacity in April 2025, and all three Licking County campuses are now grading toward a 2029 target.

Javier Reyes

Javier Reyes

Data Analyst at aterio.io